on 04-04-2016 3:53 PM
Hi All,
In Funds Management i have derived rules GL account to Commitment and Cost Center = Fund Center, Fund and Commitment
Requirement is Budget Control for Cost Center Base.
when releasing budget system is not showing in FMRP_RW_BUDCON Report and when i am posting document system is showing error
Regards,
Swamy
Thank you Gabriel Coleti
earlier they have 1 FM area for 1 Company Code now they are implemented 2nd company code and they want to implement another FM because 2nd company code have budget control only cost center base what is the reason why system is asking budget profile for new FM which was not asking in old FM area please refer below mentioned screen shot of old FM area OF15 T Code
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Swamy,
Check if you defined a budget profile at OF15 transaction code for your FM Area.
Best regards,
Gabriel Coleti
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
as far as I remember Budget profile is used for Former budget only.
And tcodes which you mentioned are for BCS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.