In MD04, I would need to change the External Procurement Text (NB) followed by Planned Order to "ExtP".
We would need to change the highlighted External Procurement Order type (NB) to "ExtP".
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Check customizing transaction OMD5.
Regards,
Caetano