on 04-30-2018 2:32 PM
You need to use Backwards scheduling with automatically created projects. The Sales Order sets the delivery date which is the finish date of the project. Then PS scheduling will work backwards from the need date to determine the start date. If you use forward scheduling the system has no point of reference for the start date.