Network Scheduling in VA01/VA02

orestis_x
Explorer
0 Kudos

Hello All and thanks for your time,

Does anybody knows, if there is a user exit or configuration that I can fill in the Start Date in order to by pass the following screen?

The configuration in OPU6 is the following:

Thank you in advance,

orestis_x
Explorer
0 Kudos

The scenario is that when creating a Sales Order and I select a configurable material and press enter, the next screen is the material characteristics. When the user fill in the characteristics value then the next screen is the one I mention above. From the saved Sales Order a Project will be created automatically.

Thank you,

Accepted Solutions (1)

Accepted Solutions (1)

kenmelching
Active Contributor
0 Kudos

You need to use Backwards scheduling with automatically created projects. The Sales Order sets the delivery date which is the finish date of the project. Then PS scheduling will work backwards from the need date to determine the start date. If you use forward scheduling the system has no point of reference for the start date.

orestis_x
Explorer
0 Kudos

Hello Ken,

I would like to have as default the current/document date. Isn't there any user exit or configuration to do that?

Thank you,

orestis_x
Explorer
0 Kudos

No, there isn't any user exit for this.