on 06-07-2016 6:31 AM
Hai Experts:
I need to know three scenario
I need to do operation wise confirmation
FERT (MMR - XYZ)
OP - 6
OP - 5
OP - 4
OP - 3
OP - 2
OP - 1
ROH ( MMR - XYF)
In this scenario i need to confirm each operation. It means that if i confirm operation 1 then roh get consumed with movement type 261 E
I was facing the problem that without confirmation operation 1 I can able to do the confirmation of 2 or 3 , but in this case system need to thro the error if i confirm operation 2 without confirming the operation 1
How to handle this process
I have MMR only for fert and roh
For my scenario the need to send operation 4 to sub con process. In routing i maintain PP02 and i create Purchase info record and if release production order pur req created for operation 4
Then i need to know that without material part now could i send the material to sub con, Because i not create material master for operation 4 only description is there
In this same scenario i need to do rework process
In House Rework Process (Rework identify before going to next operation )
In routing i create triggering point by co31 and create if i conf partically the system should thro or create rework production order. But triggering get happening but rework order is not created with specific qty
hi Albun,
part 1 -
in OPK4 transaction - select operation sequence as - I - Information when operation seq not not adher
part 2 -
pls follow the link
part 3 -
pls follow below link
regards,
Solomon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai Solomon Macwan
POINT 1
I did as per your Guideness in OPK4
After change the setting in OPK4 i run The MRP In MD50 With refer to sales order
But still the issue is not rectify
IN CO11n
Now without confirming Operation 10 i Just confirm the operation 20
Is there any other setting other then OPK4
Hello,
Please do not ask different questions or query under one discussion.
These are very basic questions please do search in this form these topic have been discussed numerous time.
For first point define the confirmation parameter in OPK4 for your order type and plant combination
Operation Sequence= E Error when Operation Sequence is not adhered to.
For second query In purchase order only operation description will appear. since no component is assigned so you can create a dummy material( non valuated) for material to send to vendor.
For third point refer SAP help link,
Trigger points - Routings (PP-BD-RTG) - SAP Library
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai R Brahmankar
After Seeing the process only i post in discuss, even i cant find the solution
POINT 1
I did as per your Guideness in OPK4
After change the setting in OPK4 i run The MRP In MD50 With refer to sales order
But still the issue is not rectify
IN CO11n
Now without confirming Operation 10 i Just confirm the operation 20
Is there any other setting other then OPK4
Hai Solomon Macwan
Thanks for your reply actually i am doing this process in DEV only, if it is work in DEV Then I will move the TR to PRD
And i check The assignment of Plant and Order type it get assigned properly
And i tried by deleting the recreated in OPK4, Still the issue is there
Thanks & Regards,
LEO
Hai R Brahmankar
Sorry to distrub u a lot, but this is urget requirement
OP00 in Check the control key
OPJB I create i set the message error Ru 442
Still the issue remain the same.
Thanks & Regards,
LEO
User | Count |
---|---|
106 | |
12 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.