on 02-08-2016 7:48 AM
Hi All,
Can anyone tell me how to create service PO from Proman (CNMM) as PR for service is already created and I have not assigned any non material on that specific activity but still not able to create PO from Proman. Kindly tell me with the help of screen shot. For reference, I'm attaching Proman Config screen sot below:
When I run CNMM, I define below parameter:
After defining above parameter, I got below screen on which 'Generate Purchase Order' is disabled.
Regards,
Faizan
Hello,
Can you please check is created PR enabled to open by ME53n transaction? or MB22?
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjeev,
I have check it's PR which is already generated but still I'm not able to create PO from PROMAN for service activity and for external activity as well. Is there any further config required for that or for service and external activity PR, we can't create PO from PROMAN.
As I have seen in help.sap that only 'MATERIAL' PO creation is mention from PROMAN, no service and external activity PO creation mention from PROMAN so kindly update me on that.
I will appreciate for your immediate response on that.
Regards,
Faizan
What is the control key on your NWA? You need to generate a PR first then use MM to convert it to a PO. If you have the configuration set up properly then it will generate a PR (it may or may not have a reservation).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
can anyone tell me above question as still issue is not resolved.
Regards,
Faizan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Faizan,
1. Since I see res/PR checked in snapshot along Generate res/PR enabled, I assume only reservation is created not PR. Still you can check in MD53 once by inputting PR number if find to make sure PR exist.
2. Check if any release strategy is assigned to PR, till PR is released you would not be able to convert PR to PO. ME54N.
Regards,
Pradeep
Hi Vengaiah,
As my activity is service with no material assigned so why reservation will be created and within activity detail, I have seen PR is already created with no release strategy on PR.
I have also released activity but still not able to create PO. Could you please tell me what could be possible reason.
Regards,
Faizan