SAP PS Organizational Structure

Organizational Structure

Each project starts with the definition and classification of the structures required for processing and the incorporation of these into the existing enterprise structure.

The Project System has no organizational structures of its own; you incorporate it into the existing structure by making assignments to the organizational units in Accounting and Logistics. It is this which enables the Project System to present data clearly and in many different ways.

Transaction Codes (T-codes ) For PS Module

Transaction For PS Module

T-Code Code Description
1. CJ20n Creation of Project
2. CJ20n Creation of WBS Elements
3. CJ20n Creation of Activities
4. CJ20n Assigning relationships to activities
5. CJ20n Assigning of milestones to activities/WBS Elements
6. CJ20n Assigning of materials of activities
7. CJ40 Planning of costs to project
8. IMCCP3 Copy Planned cost to budget
9. CJBV Availability Control of budget
10. CJ30 Assigning Budget to Project
11. CJ20n Release of Project/WBS Elements/activities
12. CN25 Confirmation of activities
13. CJ20n Maintain actual dates to milestones of WBS Elements/activities
14. CJ37 Supplement in project
15. CJ38 Return in project
16. KB21n Direct Activity Allocation
17. CNL1 Create Delivery Information
18. CNL2 Change Delivery Information
19. CNS0 Delivery from project
20. CNL3 Display Delivery Information
21. CJ2c/CJ20N Display Project
22. CJ41 Display cost planning
23. CJ31 Display Budget
24. CN28 Display Confirmations
25. CJ3B Display Document (BUDGET)
26. CN29 Cancel/Reverse of Confirmations
27. CN41 Structure Overview
28. CN42N Overview of Project Definition
29. CN43N Overview of WBS Elements
30. CN46N Overview of Networks
31. CN47N Overview of Activities
32. CN55N Overview of Sales Document items
33. CN53N Overview of Milestones
34. CN52N Components Overview
35. CN42 Enhanced Overview of Project definition
36. CN43 Enhanced Overview of WBS Elements
37. CN44 Enhanced Overview of Planned Orders
38. CN45 Enhanced Overview of Orders
39. CN46 Enhanced Overview of Networks
40. CN47 Enhanced Overview of Activities
41. CN48 Enhanced Overview of Confirmations
42. CN52 Enhanced Overview of Components
43. CN53 Enhanced Overview of Milestones
44. CNS54 Enhanced Overview of Sales and Distribution Documents
45. CNS55 Enhanced Overview of Sales Document items
46. ME5J Purchase requisitions for Project
47. ME2J Purchase Orders for Project
48. CNMM Project Oriented Procurement
49. CN60 Display change documents
50. S_ALR_87013542 Actual/Commitment/Total/Plan in Control Area Currency
51. S_ALR_87013557 Budget/Actual/Variance
52. S_ALR_87013560 Budget Updates
53. S_ALR_87013532 Plan/Actual/Variance
54. S_ALR_87013533 Plan/Actual/Commitment/Rem.Plan/Assigned
55. S_ALR_87013534 Plan1/Plan2/Act/Commitment