Production Order Type Selection
This section provides an overview of automatic selection of Order type for Production order in Discrete Manufacturing and the key configuration required for the same. |
Content
1. Order & Order Type
2. Configuration Settings required
3. Master Data required
4. Order Type Selection Process Flow
Order & Order Type
Order: Object that defines
-When, where and in which quantities which products are required or available
-Which work steps are necessary for these products and which resources are occupied by them
Order Type:
Key that differentiates orders according to their purpose. The order type contains a range of parameters which affect the way the order is processed. For example, using the order type, we can specify
-The number ranges to be used for the orders
-Which criteria are used when selecting a routing
-How the order is to be costed.
Configuration required
Order type can be defined in Plant Parameters, MRP Group Parameters and Production Scheduling Profile. Based on the field input in the material master, order type will be selected automatically. Different Order Types are maintained to depict the automatic order type selection process for the below.
- Define Order Type
Transaction Code: OPJH
Navigation: SPRO> Production> Shop Floor Control> Master Data> Order> Define Order Types
- Maintain Production Scheduler & Production Scheduling Profile
Transaction Code: OPJ9
Navigation: SPRO> Production> Shop Floor Control> Master Data> Define production scheduler
- Define Production Scheduling Profile
Transaction Code: OPKP
Navigation: SPRO> Production> Shop Floor Control> Master Data> Define production scheduling profile
- Maintain MRP Group Parameters
Transaction Code: OPPR
Navigation: SPRO> Production> Material Requirements Planning> Plant Parameters> MRP Groups> Carry Out Overall Maintenance of MRP Groups
- Maintain Plant Parameters
Transaction Code: OPPQ
Navigation: SPRO> Production> Material Requirements Planning> Plant Parameters> Carry
Out Overall Maintenance of Plant Parameters
Master Data
-
MRP Group assignment in MRP 1 view of the Material Master
-
Production Scheduler and Production Scheduling Profile assignment in Work Scheduling view of the Material Master
Order Type Selection Process Flow
Whenever Production order is created, either manually or with conversion of Planned Order, the order type is selected in the following Priority: