PS Configuration Overview
1. PROJECT SYSTEM STRUCTURE 4
1.1 Define Special Characters for Projects 8
1.2 Define Project Coding Mask 11
1.3 Define Field selection for Work Breakdown Structures 14
1.4 Define Validation 19
1.5 Maintain Substitution 24
2. DEFINE TIME PROFILES 29
2.1 Define Profiles for Time Scales 33
2.2 Define PRT Usage 36
3. ACTIVATE PROJECT MANAGEMENT IN CONTROLLING AREA39
3.1 Maintain Value categories 42
3.2 Unit Costing 45
3.3 Create / Change Planning Profile 49
3.4 Maintain Budget Profile 54
3.5 Define Tolerance Limits 57
3.6 Maintain Progress Version 60
4. SCHEDULING TYPES 63
4.1 Parameters for Network Scheduling 66
4.2 Define Database Selection Profile 69
Hello Everyone,
A Ware Welcome To You All! We are really excited to offer the
complete SAP PS configuration pack to the SAP community. This
was a much- awaited pack and we are happy to present that to
you… As you are aware that our SAP FICO, PP/QM , SD, MM/WM
HR, and PM have already achieved the best selling status and have
received lots of accolades and really helped the consultants take
their SAP knowledge and career to the next level …I am very
confident that PS configuration package will go a step forward and do
much more than that……….
For those who have been on our list and who have bought from us
earlier you all know that we have over-delivered on each of our
configuration packs and we want to do the same thing with SAP PS
config pack too… For those who have visited our site for the first
time I would like to welcome you to our site and promise you that
we would do our best to ensure that your life at the clients place would
be very comfortable…
What I have done here is given you a brief of around 69+ pages
of content in PS pack so that you can have a feel of what it would be
like in terms of structure. The whole pack is extremely voluminous,
step by step guide this is just a feeler… So I hope you enjoy this…. So
lets dive right in….
1.Project System Structure
Planning of all activities in detail is an essential process in any
project irrespective of its size and volume. Right Project
planning helps to ensure the completion of project at right
time with right amount cost involved.
It is also essential to know the amount of resource and funds
required to execute the project and also the timings of its
requirement. In an organization many tasks like construction,
installation of large machinery etc.., are carried out as projects.
Project organization is a prime and foremost step in project
structuring. Project Organization in PS helps to
 Plan the project
 Monitor the project progress
 Control the project progress
Projects can be structured based on
 Work Breakdown Structure (WBS) element
 Work package – with activities
From Finance point of view, each project is identified as
 Externally financed project
 Internally financed project
Project System Organization: -
Project system has got the following parameters.
Project definition
WBS element
Networks
Activities
The above discussed PS module elements are assigned to the
existing organizational units. I.e. these are assigned to the
existing controlling area, company code, business area, profit
center and plant.
In short we can say that there is no independent org structure
for PS module like SD and MM. The PS parameters are
assigned to the existing organizational units at different levels.
Let us discuss the possible assignments of each PS elements
with existing org. structure.
Project Definition:
Project Definition is the process of defining the project with its
objective, Accounting information and logistic related
information.
Accounting information:-
Controlling Area
Company code
Business Area
Plant
Location
Profit center
Currency
Budget profile
Interest calculation profile
Planning profile
Investment profile
Result Analysis key
Logistic information
Network profile
WBS Scheduling profile
Person responsible
Start & End date
Factory calendar
Time unit
WBS Element: -
WBS element is a master data used for projects. The usage of
WBS is
 Organizes the project task in an order
 Process planning, cost planning, capacity planning
 Costing and controlling
 To know the amount of work involved in a project
WBS is created with reference to the project definition. The
data maintained under project definitions are copied into WBS
WBS Accounting information:-
 Currency – Copied from projection profile.
Can be changed only if company code
currency is different from controlling
area and there must NOT be any
budget, commitments exist for the
WBS element.
 Company code
 Business area
 Profit center
 Plant
Network: -
Network represents flow of task in a project. Tasks performed
with WBS such as planning, controlling etc. can be done with
network also. The structure of the network is similar to that of
production order and maintenance order.
Network can be assigned to
 Project definition
 WBS
 Time sheet entry
Activities: -
Activities indicate the sequence of any process. Activities
contains
Duration
Start and finish
Requirement of resources
Cost requirements
Activities can be
Internally processed
Externally processed
Service related
General cost activities
Now let us see what is there in the configuration for PS
structure.
The project definition contains various profiles from costing
point of view. We shall start from WBS structure.
Define Special Characters for Projects
BACKGROUND
This configuration setting enables to define how the project
number is coded for editing.
Following parameters are controlled in this setting to edit the
project number.
 Length of the key for project coding - Max. five
 Mandatory length of the project coding – whether all five
must be filled or not.
 Special characters allowed for entering WBS
SCENARIO
Define special character for projects.
INSTRUCTION
Follow the Menu Path: IMGProject System  Structures 
Operative Structures Work Breakdown Structures (WBS) 
Project Coding Mask  Define Special characters for Projects
Click or
use OPSK in the command field and press Enter.
Maintain fields as explained below
Field Name Value and Description of field
Length of key for coding of the project
definition and WBS elements.
Possible entries are
E.g.5 indicates maximum
It must be set carefully before creating any
projects.
We will proceed with 1 in our example.
Key used to specify project coding and
WBS element must of same length as it is
defined here.
E.g. Leave it blank not to restrict the length
of project coding and WBS element.
To help entering the WBS element in the
work break down structure, this special
key is defined.
E.g. Enter ". To enter a new WBS element
under WBS element, it is enough to enter "
and new number. E.g. say new number is
30, then system will maintain the number
with all prefixes and the number 30.
Special character used to limit the
segments in the coding.
E.g. / to limit with the character / between
the segments.
Check in this tick box will allow only the
coded project numbers within the project
system.
E.g. tick the check box.
This field is used for automatic number
assignment.
E.g. Leave it blank.
Click
Click
Impact of this configuration in Master Data /
Transaction
Project numbering will be as per this project special character
setting.
Define Project Coding Mask
BACKGROUND
This configuration setting enables to create masks for editing
the project number.
Project coding mask is helpful to simplify the complex project
numbers. It is also used to indicate the position of the WBS
element.
SCENARIO
Discuss the project coding mask. Ex: /000-XXX-000/XXXX
INSTRUCTION
Follow the Menu Path: IMGProject System  Structures 
Operative Structures Work Breakdown Structures (WBS) 
Project Coding Mask  Define Project Coding Mask
Click
Or Enter OK02 in the command field – press Enter.
Click
Maintain fields as explained below
Field Name Value and Description of field
Length of key for coding of the project
Note:- Here the project id can be maximum
of 1 digit as we have set up the PL field in
the above setting as 1.
Define the coding mask for project
definition
0 (zero) – only numeric characters
X – alpha numeric characters
Maintain description of coding mask
Tick in this check box will not enable the
new request for WBS element, project
definition or appropriation request to be
created with this masking code.
Tick in this check box will not allow
creating coding mask for standard project
or WBS element.
Click
Click
Impact of this configuration in Master Data /
Transaction
Project coding mask created here will be used while creation
project definition, WBS element or appropriate request.
Define Field selection for Work Breakdown Structures
BACKGROUND
This configuration setting enables to define the WBS field
selection.
Through this configuration setting it is possible to make a field
mandatory, optional, hide or view only.
It is required to make certain field to make mandatory
according to the business requirement.
SCENARIO
Make Project Description field as mandatory for company code
3000
INSTRUCTIONS
Follow the Menu Path: IMGProject System  Structures 
Operative Structures Work Breakdown Structures (WBS) 
User Interface Settings  Define Field Selection for Work
Breakdown Structures
Click
Double click
Double click on Description field
Click on
Click
Enter the company code as “1000”
select radio button
Double Click to influence any of one fields
Click
Double click
Similarly as explained above, field selection can be done for
WBS element also.
Note:- the procedure is same for Network field selection as well.
Impact of this configuration in Master Data /
Transaction
When creating project definition CO area become mandatory
entry
Define Validation
BACKGROUND
This configuration setting enables to define validation.
Use validations to check values and value combinations that
users enter in the Project System. Validation can be carried
out at various points in time.
Following are the steps to be carried-out:
 Enter a name for the validation.
 The application area is proposed by the system.
 Enter a call-up point when the validation should be
carried out.
 Create a validation step or select an existing one.
 Select the field that you want to use for the validation.
 Enter a prerequisite and specify how the validation
should be carried out.
 For each validation step enter a prerequisite, a check and
a validation message. The message is issued when the
prerequisite is met and when the value does not check.
SCENARIO
Discuss validation defining.
INSTRUCTION
Follow the Menu Path: IMGProject System  Structures 
Operative Structures Work Breakdown Structures (WBS) 
Maintain Validations
Click
Click the required object to create validation E.g.
Click
Enter validation name. e.g. ZLEGL02 and text as “check profit
center”
Click
Click to enter any prerequisite
Double click
Click
Click
Enter the project definition to which the check is to be
applicable.
Double Click
double click
Click
Click
Enter the value which must be maintained as profit center for
project definition with W
Click
Double Click
Enter message type
Enter message number.
Message variable entered if the message contains any variable.
Example: -
Message:- "Acount $ is not allowed in company code $"
Output field 1: BSEG-HKONT (=400000)
Output field 2: BSEG-BUKRS (=0001)
Click
Message appear at the bottom
Maintain Substitution
BACKGROUND
This configuration setting enables to define substitution.
Use substitutions to replace values and value combinations in
the Project System. In addition you can define several
interdependent substitution statements for future use.
Following are the steps to be carried-out:
 Enter a name for the Substitution.
 The application area is proposed by the system.
 Enter a call-up point when the substitution should be
carried out.
 Create a substitution step or select an existing one.
 Select the field that you want to use for the substitution.
 Enter a prerequisite and specify how the substitution
should be carried out.
SCENARIO
Discuss substitution defining.
INSTRUCTION
Follow the Menu Path: IMGProject System  Structures 
Operative Structures Work Breakdown Structures (WBS) 
Maintain Substitution
Click
Click on the object where the substitution is to be created. E.g.
whether on project definition or on WBS element
Click to create rule or click to create
substitution
Enter substitution key and text
Click
Enter the step number and text
Double click
Double click
Click
Click
Enter the finish date
Click
Double click
Click
Select the field person responsible
Click
Select the appropriate radio button. E.g.
Click
Enter the required value
Click
2.Define Time Profiles
BACKGROUND
This configuration setting enables to define the time profiles.
Time profile is used to specify various working time periods
used in the project planning board.
Time profile contains the evaluation period and planning
period.
Evaluation period is the time frame for working with and
displaying data in the project planning board. Beyond the
evaluation period, it is not possible to work with and display
the data in the planning board.
Planning period is used to define the time frame for carrying
out current planning in the project planning board.
 If the start date is beyond the current date, the planning
period begins with the start date.
If the start date is earlier than the current date, the
planning period begins with the current date.
SCENARIO
Discuss the time profile.
INSTRUCTION
Follow the Menu Path: IMGProject System  Structures
 Project Planning Board  Define Time Profiles
Click
Click
Maintain fields as explained below
Field Name Value and Description of field
Key identifying the time profile. Enter key
and description. E.g.
Key indicates the type of entry to be made.
I.e. Monthly, yearly. Select from available
entries
for
evaluation period
E.g. L to indicate years
Enter start date. E.g. 0. Indicates start
from 0 years
Start date is the date of the first day of the
period to which the data required to be
evaluated.
System determines the first date with entry
here along with entry type.
E.g. today is 14.01.2005
Type of entry: G
Start: -10
Finish : +20
evaluation
period.
For
This generates an evaluation period from
04.01.2005 to the 03.02.2005.
Enter finish date. E.g. 2 indicates
evaluation allowed for next two years.
Similarly maintain the entries as shown below for planning
period.
Click
Click
Click
Impact of this configuration in Master Data /
Transaction
Time profile defined here can be assigned to the project
planning board in the subsequent settings.
Define Profiles for Time Scales
BACKGROUND
This configuration setting enables to define Time scale
profile.
Time scale profile defines the properties of all possible
scales.
The possible time scale headings are
 Yearly split
 Quarterly split
 Monthly split
 Weekly split
 Daily split
 Hourly split
 Minute split
 Shift split
For each time scale heading maximum and minimum time
scale must be maintained.
SCENARIO
Discuss the profile for time scale.
INSTRUCTION
Follow the Menu Path: IMGProject System  Structures
 Project Planning Board  Define Profiles for Time Scales
Click
Click to create new entries.
Note:- it is always suggested to copy from the existing
standard entry.
Select any standard row. E.g. second row
Click
Enter the new time scale profile. E.g. ZPS_PROAAA
As the standard setting is sufficient nothing much to
change other than specifying the bar chart width in mm for
minimum and maximum.
Click
Click
Click
Impact of this configuration in Master Data /
Transaction
Profile for time scale defined here will be used in the project
planning board setting.
Define PRT Usage
BACKGROUND
This configuration setting enables to define the PRT usage.
Production Resource Usage controls the usage of PRT in
different task list and applications.
It is possible to allow the usage of PRT only in networks.
SCENARIO
Discuss the PRT usage setting.
INSTRUCTION
Follow the Menu Path: IMGProject System  Production
Resource Tool  General Data  Define PRT Usage
Click
Click to create new entries, SAP standard usage is
sufficient to work with. Let us discuss the standard usage
003.
Select usage 003
Double Click in the left side
Maintain the task list type under the usage.
Click
Click
Click
Impact of this configuration in Master Data /
Transaction
When creating the PRT, usage can be defined as per the
settings here.
3.Activate Project Management in Controlling
Area
BACKGROUND
This configuration setting enables to activate project
management in controlling area.
This setting also enables to activate the commitment
management for a controlling area.
SCENARIO
Discuss activation of project management in controlling area.
INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Costs 
Activate Project Management in Controlling Area
Click
Available controlling areas are displayed at right side. Select
the desired row
To the desired controlling area activate the projects( )
and commitments management ( )
Note:- There could be other settings related to CO module, like
assigning the company code to controlling area etc.. but here
the point of activating project management only explained.
Click
Maintain Value categories
BACKGROUND
This configuration setting enables to define value categories.
Value categories are required for
 Updating project information database
 Calculating interest on projects
 Defining reports
 Updating quantities in project info.
SCENARIO
Discuss maintenance of value categories.
INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Costs 
Value Categories  Maintain Value categories
Click
Enter the controlling area
Click
Click
Enter the value category. E.g. Z01
Enter the description for value category maintained.
Select the relevant radio button as explained below.
E.g. Cost radio button to the purpose of posting of costs or
outgoing payments.
Revenues to the purpose of posting revenues and incoming
payments
SKFw.Tt to the purpose of posting statistical key figure with
total characteristic value
SKF FVA to the purpose of posting statistical key figure with
fixed value characteristic
Click
Unit Costing
Unit costing will be where you have information on sources of
supply, quantities, and prices. Plan overall or annual values
for unit costing.
Costing variant is to combine all the controlling parameters for
costing. Costing variant represents the link between the
application and customizing because all costing run must
reference a costing variant as they are made and stored.
The costing variant controls the following parameter.
 Costing variant contains the valuation variant and
costing type.
 Valuation variant controls price to pickup for material,
subcontracting and external processing.
 Valuation variant contains the costing sheet also (over
head calculation)
BACKGROUND
This configuration setting enables to define the variants for
Unit costing.
SCENARIO
Define / discuss costing to create variant.
INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Costs 
Manual cost planning in WBS  Unit Costing  Create
Costing Variant.
Or Enter OKKT in the command field – press Enter.
Maintain the fields as explained below
Field Description
This field sets how the cost to
be estimated based on the
materials, Production orders
with controlling, Internal
orders and sales orders.
Based on the type of business scenario costing variant is
created.
Click on new entries
In Control Tab maintain the field as explained below
Field Description
This field requires how the
cost estimate to be used. Ex:
unit cost est. for proj
This field specifies the prices
the system selects to valuate
the quantity structure of a
cost estimate with quantity
structure or of the order, or to
valuate the costing items of a
unit cost estimate. Ex:
Planned valuation –orders.
This field sets how the date
control of a cost estimate is
handled. Ex: Mod.std cost est.
dates
Click on the assignment tab
Click on to verify the variant. To verify the variant – variant
to be saved.
Click Save .
If the Variant is ok – system will give message
Impact of this configuration in Master Data /
Transaction
Based on the business scenario use the costing variant
Create / Change Planning Profile
BACKGROUND
This configuration setting enables to create / change planning
profile. Planning profile is required to plan the cost methods.
Following controls are available in the planning profile.
Time frame – can specify which values are the to planned and
their fiscal years.
Value display - to display the decimal places and decimal
factor
Detail planning – values for cost element planning ,activity
Input planning and cost planning.
Planning profile is used
 For all WBS elements or only on planning elements ,
 Bottom-Up planning within hierarchical planning ,
 Automatic revenue planning.
Based on the settings one can decide whether the system
updates plan revenues on the corresponding billing elements.
Profile can be Cost planning for investment programs or
investment measures, and for appropriation requests.
SCENARIO
Define / Discuss Planning profile.
INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Costs 
Planned Costs  Manual cost planning in WBS 
Hierarchical Cost Planning  Create / Change Planning
Profile.
Or Enter OPSB in the command field – press Enter.
Click on the new entries or copy the existing plan based on
the business scenario.
Maintain the fields as explained below
Field Description
This sets the control
parameter for the planning.
In the Manual Planning -
when the Bottom up planning
indicator is set, the system
automatically carries out the
total up function in structure
planning for costs and
revenues each time you save
and check data. The structure
plan value for the higher level
WBS item is the total of all the
plan values for the WBS
elements directly below it.
To ensure that the structure
plan values for the whole
project structure are uniform,
must access the structure
planning for the whole project
and check and save the
values.
This field sets cost planning is
possible in only those WBS
elements are defined as
Planning elements. Can carry
the cost planning in any WBS
elements when the indicator is
set.
This field require the time
frame in future – means how
far can far.
Based on the scenario can
mention Past and start time
frames.
This field sets the values
required in total and annual
years.
This field sets whether any
decimal places and its scaling
factor required for the
planning profile.
This field sets the cost
element group as primary
costs where goods brought in
externally like raw materials ,
operating supplies ,
services ,etc based on the
chart of accounts. Ex:
OAS_PRIM
This field sets to summarize
cost elements of the same
types in reports. Ex:
OAS_REVEN
This field specifies the cost
center group of sender
for which activity types
are planned. EX: H1400
This field sets each activity
type in this group can appear
as a sender activity type in
activity input planning. EX:A1
This field sets a group of
stastical key figure used in
reporting to process multiple
key figures in a
single transaction. EX:
STAT_9000
This field sets how the cost
estimate is performed and
valuated. EX: INV1
This field sets the exchange
rate in the system and value
dates determines daily
exchange rates applies
For currency translation. EX:
001
This field sets the types of
planning currency based on
Controlling areacurrency /
object currency / Translation
currency. EX: Controlling area
currency.
This field sets how the
revenue planning should
happen automatically through
quotation or sales order..
This field requires to enter the
type of revenue element for
billing plan to WBS element.
Click Save .
Impact of this configuration in Master Data /
Transaction
Based on the planning profile – one can carry out Cost
Planning by entering values in the cost plan column using
CJ30 transaction code.
Maintain Budget Profile
BACKGROUND
This configuration setting enables to control the budget for the
Project.
SCENARIO
Define / Discuss budget profile.
INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Costs 
Budget  Maintain Budget Profiles.
Or Enter OPS9 in the command field – press Enter.
Click on new entries or copy the existing profile based on the
Business scenario.
Maintain fields as explained below
Field Description
This field sets type profile type
and description. Ex: 1000
This field sets the time frames
which can in past, future or
start and enable total and
annual values. Ex: enable in
Future - 3
This field sets WBS element
using this budget profile can
only be budgeted if the WBS
element or a WBS element
above it in the hierarchy is
assigned to a program
position ofan investment
program with the correct
program type. Ex: 1000.
This field sets type of control
that should be available while
budgeting and how the
activation type should be. i.e
Automatic activation during
budget allocation.
EX : 1 –means automatic
allocation during budget
activation.
This field sets a WBS element
using this budget profile can
only be budgeted if the WBS
element or a WBS element
above it in the hierarchy is
assigned to a program
position ofan investment
program with the correct
program type. Ex: 1000.
Based on the type of business scenario use the control
parameters for network scheduling
Click Save .
Impact of this configuration in Master Data /
Transaction
Based on the business scenario define and use the control
parameters.
Define Tolerance Limits
BACKGROUND
This configuration setting enables to give tolerance limit for
the budget profile.
The Tolerance range /limits the budget if any project overruns
the allocated cost / money.
Activate availability control for a certain budget profile. Can
specify one or more tolerance limits for each activity group for
a budget profile.
Selected actions (warning, warning with mail to person
responsible for project, error message) are triggered when
these limits are reached.
Tolerance limit for all activity groups can be chosen as activity
group ++ which make entry easier. Tolerance limit for all
activity groups can be used if it is not required to define a
separate tolerance limit for each activity group.
It is possible to define a limit for a specific activity group in
addition to a tolerance limit defined for all activity groups.
This additional tolerance limit has priority over the generally
valid tolerance limit.
SCENARIO
Define / Discuss Tolerance limits.
INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Costs 
Budget  Define Tolerance Limits.
Click on new entries if the controlling area belong to the
Controlling does not exists. If exists define the tolerance limits.
Field Description
This field tells about the
controlling area. Ex: 2000
This field sets the budget
profile to the controlling area.
Ex: 1000
This field tells about target
group of the activity type. Ex:
++ indicates that target group
belongs to all activity types.
This field sets activity type.
Ex: 1 /2 / 3.
This field sets how much the
usage should be for the said
budget profile.
This field tells about difference
between the assigned funds
and the budget exceeds the
absolute variance, availability
control triggers the
appropriate action.
This field tells about the
controlling area currency.
Click Save .
Impact of this configuration in Master Data /
Transaction
Based on the business scenario define the budget tolerance
limits.
Maintain Progress Version
BACKGROUND
This configuration setting enables to define the progress
version.
Progress version is required to create control data for
calculating the % of completion and the earned value.
Note:- This is to be done in discussion with CO team
SCENARIO
Discuss progress version .
INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Progress 
Progress Analysis  Maintain Progress Version
Click
Click to create new entry
Maintain the fields as explained below
Field Description
Key identifying the controlling
area. Enter controlling area
Key identifying the progress
version. Enter progress
version and description
Key identifying the plan
version. Note:- the CO version
must have exclusive use 03
i.e. earned value analysis.
Earned value is calculated by
applying the % of completion
of the cost amount. This
defines which cost amount is
to be used. Available entries
are
Value used for weighting in
the aggregation of the % of
completion. Possible entries
are
Key identifying the type of
planning to be used. Available
entries are
This key to determine whether
either:
 the earliest date is set to
the latest date of the
activity or
 The latest date is set to
the earliest date of the
activity.
Tick in this check box will
enable the system to use the
system uses an existing
method if the method is not
maintained.
Click
4.Scheduling Types
BACKGROUND
This configuration setting enables to define the scheduling
types to the projects.
Scheduling types governs the way scheduling is to be
performed.
SCENARIO
Define / Discuss scheduling types.
INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Dates 
Scheduling  Define scheduling types.
Or Enter OPJN in the command field – press Enter.
Field Description
This indicator sets the
scheduling type as Forward
for orders and Networks
means schedules from the
start date.
This indicator sets the
scheduling type as backward
for orders and Networks –
means schedules from the
Finish date.
This indicator sets the
capacity requirements to
calculate. Distributed across
the periods based on the types
of dates.
This indicator sets as today’s
date for scheduling.
This indicator sets the time to
enter the basic dates for the
production orders.
Based on the type of business scenario use the scheduling
type.
Click Save .
Impact of this configuration in Transaction
When performing the scheduling in the project, scheduling will
be carried out as per the setting maintained here.
Parameters for Network Scheduling
BACKGROUND
This configuration setting enables to define parameter for
network scheduling.
Network scheduling contains settings for
 Dates adjustment
 Type scheduling to be performed
 Control to allow start day in the past
 Reduction type
This setting is performed for the combination of Plant, order
type and Production scheduler.
SCENARIO
Define / Discuss control parameters of scheduling.
INSTRUCTIONS
Follow the Menu Path:- IMGProject System  Dates 
Scheduling  Specify Parameters for Network scheduling.
Or Enter OPU6 in the command field – press Enter.
Field Description
Key identifying the plant.
E.g. 1000
Key identifying order type.
E.g. PS05
Key identifying the production
scheduler.
E.g. *
This control determination of basic
dates to the element or to its
dependant requirements during
lead time scheduling.
Type of scheduling to be applied to
this order type or network type.
Indicates whether the past start
date is allowed. If it is to be
allowed, enter the number of days.
E.g. Leave it blank.
Tick in this check box
automatically schedule the network
on saving.
Tick in this check box displays
scheduling log automatically during
each scheduling
e.g. Leave it blank
Tick in this check box considers the
exact time of break during
scheduling.
e.g. Leave it blank
Tick in this check boxwill not
consider the partially confirmed
operations.
E.g. Leave it blank
This tick mark to schedule the
component on latest scheduled
date.
Indicates what reduction type is to
be employed
Number of reduction level to be
applied.
Click Save
Impact of this configuration in Master Data /
Transaction
During network creation, scheduling will be done according to
the settings maintained here.
Define Database Selection Profile
BACKGROUND
This configuration setting enables to define Database selection
profile.
This is the process of picking up the desired objects and fields
from the database for information analysis purpose.
Note: - Standard SAP setting will be sufficient in most of the
cases. Let us discuss the standard setting and understand.
SCENARIO
Discuss the Database selection profile.
INSTRUCTION
Follow the Menu Path: IMGProject System Information
system  Selection  Define Database Selection Profile
Click
Field Name Value and Description of field
Tick in this check box will enable only last
person who made changes only to make
further changes
Tick in this check box will pickup its
superior objects also. E.g. WBS elements
are selected as objects, but it will pickup
its project definition also.
Changes can be made only through the
configuration setting if this check box is
ticked.
Tick in this check box will pickup project
definition from the database
If not ticked, project can not be made as a
selection criteria as project definition does
not appear in the selection screen.
Tick in this check box will pickup sales
order and customer quotation for selection
Tick in this check box will pickup material
component from Database.
Tick in this check box will pickup WBS
element
Tick in this check box will pickup
hierarchy of sub element of WBS.
Tick in this check box will stipulate
network and orders assigned to WBS.
Tick in this check box will pickup network
assigned to WBS element
Tick in this check box will pickup the
production order, process orders assigned
to WBS
Similarly all check boxes which are ticked are selected from
the data base.
Click
Click
Impact of this configuration in Master Data /
Transaction
Information system when displaying the objects, it will pickup
data from database as per the configuration maintained here.
That’s it then… The entire PS configuration pack comes
in 7 voluminous power packed CDS f u l l o f m e a t y c o n te nt and
each sub module in SAP PS is broken into Configuration, End
user and Power point. There are tons of bonuses which you get
along with this pack including complete Integration documents,
PS Interview questions and answers and a boatload of step by
step guides……… You can take advantage of the special offer by
visiting the site at
http://www.sap-topjobs.com/SpecialPP/sapps20071123.html
All our packs are shipped thru FedEx and reaches you in three
days time. One more thing this configuration pack is compatible with
version 4.7, version 5.0 and 6.0 So you really do have to worry about
the version at all.. We have taken care of that… Also all future
version changes will be provided as free updates to you. So you can
sit back relax and play the music ….
What I want from you now is to do yourself a favour by bringing
the brains and wisdom of SAP PS Experts with more than
12+yrs of implementation experience to your drawing room today.
Do it right now my dear friend and take your SAP career to the
next level…. You will love it I promise you….
http://www.sap-topjobs.com/SpecialPP/sapps20071123.html
www.sap-topjobs.com

More Related Content

What's hot

How to extend an outbound i doc
How to extend an outbound i docHow to extend an outbound i doc
How to extend an outbound i docrupesh chouhan
 
SAP Project Intelligence Network for Construction
SAP Project Intelligence Network for ConstructionSAP Project Intelligence Network for Construction
SAP Project Intelligence Network for ConstructionComit Projects Ltd
 
Currency conversion in bi 7.0
Currency conversion in bi 7.0Currency conversion in bi 7.0
Currency conversion in bi 7.0gireesho
 
Configure and customize automatic credit management
Configure and customize automatic credit managementConfigure and customize automatic credit management
Configure and customize automatic credit managementAndrea Graziani
 
Capex opex
Capex opexCapex opex
Capex opexRaju_p1
 
Ps training mannual ( configuration )
Ps training mannual ( configuration )Ps training mannual ( configuration )
Ps training mannual ( configuration )Soumya De
 
Copying number ranges in SAP FICO ECC
Copying number ranges  in SAP FICO ECCCopying number ranges  in SAP FICO ECC
Copying number ranges in SAP FICO ECCSrinivas Rao
 
Sap mm-configuration-step-by-step-guide-121029154857-phpapp01
Sap mm-configuration-step-by-step-guide-121029154857-phpapp01Sap mm-configuration-step-by-step-guide-121029154857-phpapp01
Sap mm-configuration-step-by-step-guide-121029154857-phpapp01Ramesh G
 
SAP Cloud Platform Product Overview
SAP Cloud Platform Product OverviewSAP Cloud Platform Product Overview
SAP Cloud Platform Product OverviewSAP Cloud Platform
 
Salesforce DX の始め方とパートナー様成功事例
Salesforce DX の始め方とパートナー様成功事例Salesforce DX の始め方とパートナー様成功事例
Salesforce DX の始め方とパートナー様成功事例Salesforce Developers Japan
 
Wp sap data_migration
Wp sap data_migrationWp sap data_migration
Wp sap data_migrationBiswajit Kar
 
sap-ps-project-systems
 sap-ps-project-systems sap-ps-project-systems
sap-ps-project-systemshollabackgirl1
 
Ps training mannual power users
Ps training mannual   power usersPs training mannual   power users
Ps training mannual power usersSoumya De
 
How to add new Object Link in SAP DMS
How to add new Object Link in SAP DMSHow to add new Object Link in SAP DMS
How to add new Object Link in SAP DMSAssaf Sheinrok
 
Balco ps configuration manual
Balco ps configuration manualBalco ps configuration manual
Balco ps configuration manualJaideep Kulkarni
 

What's hot (20)

How to extend an outbound i doc
How to extend an outbound i docHow to extend an outbound i doc
How to extend an outbound i doc
 
SAP Project Intelligence Network for Construction
SAP Project Intelligence Network for ConstructionSAP Project Intelligence Network for Construction
SAP Project Intelligence Network for Construction
 
Currency conversion in bi 7.0
Currency conversion in bi 7.0Currency conversion in bi 7.0
Currency conversion in bi 7.0
 
SAP MM Config Guide
SAP MM Config GuideSAP MM Config Guide
SAP MM Config Guide
 
Configure and customize automatic credit management
Configure and customize automatic credit managementConfigure and customize automatic credit management
Configure and customize automatic credit management
 
SAP PPM 6.0 powered by HANA
SAP PPM 6.0 powered by HANASAP PPM 6.0 powered by HANA
SAP PPM 6.0 powered by HANA
 
Capex opex
Capex opexCapex opex
Capex opex
 
Ps training mannual ( configuration )
Ps training mannual ( configuration )Ps training mannual ( configuration )
Ps training mannual ( configuration )
 
Copying number ranges in SAP FICO ECC
Copying number ranges  in SAP FICO ECCCopying number ranges  in SAP FICO ECC
Copying number ranges in SAP FICO ECC
 
Sap mm-configuration-step-by-step-guide-121029154857-phpapp01
Sap mm-configuration-step-by-step-guide-121029154857-phpapp01Sap mm-configuration-step-by-step-guide-121029154857-phpapp01
Sap mm-configuration-step-by-step-guide-121029154857-phpapp01
 
SAP Cloud Platform Product Overview
SAP Cloud Platform Product OverviewSAP Cloud Platform Product Overview
SAP Cloud Platform Product Overview
 
Salesforce DX の始め方とパートナー様成功事例
Salesforce DX の始め方とパートナー様成功事例Salesforce DX の始め方とパートナー様成功事例
Salesforce DX の始め方とパートナー様成功事例
 
Wp sap data_migration
Wp sap data_migrationWp sap data_migration
Wp sap data_migration
 
sap-ps-project-systems
 sap-ps-project-systems sap-ps-project-systems
sap-ps-project-systems
 
Ps training mannual power users
Ps training mannual   power usersPs training mannual   power users
Ps training mannual power users
 
Tamm40 SAP MM
Tamm40 SAP MMTamm40 SAP MM
Tamm40 SAP MM
 
SAP Project system.pptx
SAP Project system.pptxSAP Project system.pptx
SAP Project system.pptx
 
How to add new Object Link in SAP DMS
How to add new Object Link in SAP DMSHow to add new Object Link in SAP DMS
How to add new Object Link in SAP DMS
 
Transfer pricing in sap
Transfer pricing in sapTransfer pricing in sap
Transfer pricing in sap
 
Balco ps configuration manual
Balco ps configuration manualBalco ps configuration manual
Balco ps configuration manual
 

Viewers also liked

Basics sap external service management
Basics sap external service managementBasics sap external service management
Basics sap external service managementSachin S Bhalekar
 
Here are the 16 pricing elements in pricing procedure and description for each
Here are the 16 pricing elements in pricing procedure and description for eachHere are the 16 pricing elements in pricing procedure and description for each
Here are the 16 pricing elements in pricing procedure and description for eachvishalsap84
 
Hype vs. Reality: The AI Explainer
Hype vs. Reality: The AI ExplainerHype vs. Reality: The AI Explainer
Hype vs. Reality: The AI ExplainerLuminary Labs
 
Study: The Future of VR, AR and Self-Driving Cars
Study: The Future of VR, AR and Self-Driving CarsStudy: The Future of VR, AR and Self-Driving Cars
Study: The Future of VR, AR and Self-Driving CarsLinkedIn
 

Viewers also liked (6)

Basics sap external service management
Basics sap external service managementBasics sap external service management
Basics sap external service management
 
Project sheild
Project sheildProject sheild
Project sheild
 
Here are the 16 pricing elements in pricing procedure and description for each
Here are the 16 pricing elements in pricing procedure and description for eachHere are the 16 pricing elements in pricing procedure and description for each
Here are the 16 pricing elements in pricing procedure and description for each
 
Sap mm-end-user-manual
Sap mm-end-user-manualSap mm-end-user-manual
Sap mm-end-user-manual
 
Hype vs. Reality: The AI Explainer
Hype vs. Reality: The AI ExplainerHype vs. Reality: The AI Explainer
Hype vs. Reality: The AI Explainer
 
Study: The Future of VR, AR and Self-Driving Cars
Study: The Future of VR, AR and Self-Driving CarsStudy: The Future of VR, AR and Self-Driving Cars
Study: The Future of VR, AR and Self-Driving Cars
 

Similar to Sapps

Project system module online training
Project system module online trainingProject system module online training
Project system module online trainingmagnific2220
 
Project system module online training
Project system module online trainingProject system module online training
Project system module online trainingmagnific2222
 
Understanding Code Formats in Vista
Understanding Code Formats in VistaUnderstanding Code Formats in Vista
Understanding Code Formats in VistaVisibility by Design
 
Creating new unit of measure in sap bw
Creating new unit of measure in sap bwCreating new unit of measure in sap bw
Creating new unit of measure in sap bwRajat Agrawal
 
Software Development: Fixed Price Model Features
Software Development: Fixed Price Model FeaturesSoftware Development: Fixed Price Model Features
Software Development: Fixed Price Model FeaturesVladimir Tursin
 
Sap ps module tutorial
Sap ps module tutorialSap ps module tutorial
Sap ps module tutorialachyuth10
 
Introduction to sap project systems
Introduction to sap project systemsIntroduction to sap project systems
Introduction to sap project systemsSoumya De
 
Sappsmoduletutorial 130129062429-phpapp02
Sappsmoduletutorial 130129062429-phpapp02Sappsmoduletutorial 130129062429-phpapp02
Sappsmoduletutorial 130129062429-phpapp02Subhasis Sarkar
 
Leveraging IBM Cognos TM1 for Merchandise Planning at Tractor Supply Company ...
Leveraging IBM Cognos TM1 for Merchandise Planning at Tractor Supply Company ...Leveraging IBM Cognos TM1 for Merchandise Planning at Tractor Supply Company ...
Leveraging IBM Cognos TM1 for Merchandise Planning at Tractor Supply Company ...QueBIT Consulting
 
Maintaining comment fields directly in planning layouts using the transaction...
Maintaining comment fields directly in planning layouts using the transaction...Maintaining comment fields directly in planning layouts using the transaction...
Maintaining comment fields directly in planning layouts using the transaction...Janakiram Yelike
 
Variables in sap bi
Variables in sap biVariables in sap bi
Variables in sap bishabari76
 
Determining Requirements Complexity - White Paper
Determining Requirements Complexity - White PaperDetermining Requirements Complexity - White Paper
Determining Requirements Complexity - White PaperSaurabh Goel
 
Hr structural auths
Hr   structural authsHr   structural auths
Hr structural authshkodali
 
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docxgerardkortney
 
SuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
SuccessFactors 2H 2021 Sneak Peek by Deloitte GermanySuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
SuccessFactors 2H 2021 Sneak Peek by Deloitte GermanyChristoph Pohl
 
© SAP SE CASE STUDY .docx
 © SAP SE   CASE STUDY .docx © SAP SE   CASE STUDY .docx
© SAP SE CASE STUDY .docxmayank272369
 

Similar to Sapps (20)

Project system module online training
Project system module online trainingProject system module online training
Project system module online training
 
Project system module online training
Project system module online trainingProject system module online training
Project system module online training
 
Understanding Code Formats in Vista
Understanding Code Formats in VistaUnderstanding Code Formats in Vista
Understanding Code Formats in Vista
 
Ps business blueprint
Ps business blueprintPs business blueprint
Ps business blueprint
 
Creating new unit of measure in sap bw
Creating new unit of measure in sap bwCreating new unit of measure in sap bw
Creating new unit of measure in sap bw
 
Software Development: Fixed Price Model Features
Software Development: Fixed Price Model FeaturesSoftware Development: Fixed Price Model Features
Software Development: Fixed Price Model Features
 
Sap ps module tutorial
Sap ps module tutorialSap ps module tutorial
Sap ps module tutorial
 
Introduction to sap project systems
Introduction to sap project systemsIntroduction to sap project systems
Introduction to sap project systems
 
Sappsmoduletutorial 130129062429-phpapp02
Sappsmoduletutorial 130129062429-phpapp02Sappsmoduletutorial 130129062429-phpapp02
Sappsmoduletutorial 130129062429-phpapp02
 
Leveraging IBM Cognos TM1 for Merchandise Planning at Tractor Supply Company ...
Leveraging IBM Cognos TM1 for Merchandise Planning at Tractor Supply Company ...Leveraging IBM Cognos TM1 for Merchandise Planning at Tractor Supply Company ...
Leveraging IBM Cognos TM1 for Merchandise Planning at Tractor Supply Company ...
 
Maintaining comment fields directly in planning layouts using the transaction...
Maintaining comment fields directly in planning layouts using the transaction...Maintaining comment fields directly in planning layouts using the transaction...
Maintaining comment fields directly in planning layouts using the transaction...
 
Variables in sap bi
Variables in sap biVariables in sap bi
Variables in sap bi
 
Determining Requirements Complexity - White Paper
Determining Requirements Complexity - White PaperDetermining Requirements Complexity - White Paper
Determining Requirements Complexity - White Paper
 
Hr structural auths
Hr   structural authsHr   structural auths
Hr structural auths
 
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
 
Blue book
Blue bookBlue book
Blue book
 
SuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
SuccessFactors 2H 2021 Sneak Peek by Deloitte GermanySuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
SuccessFactors 2H 2021 Sneak Peek by Deloitte Germany
 
© SAP SE CASE STUDY .docx
 © SAP SE   CASE STUDY .docx © SAP SE   CASE STUDY .docx
© SAP SE CASE STUDY .docx
 
SAP PS Intro
SAP PS IntroSAP PS Intro
SAP PS Intro
 
Chaitra
ChaitraChaitra
Chaitra
 

Recently uploaded

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 

Recently uploaded (20)

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 

Sapps

  • 1. OVER VIEW OF SAP PS Configuration Pack Published by Team of SAP Consultants at SAPTOPJOBS Visit us at www.sap-topjobs.com Copyright 2010-12@SAPTOPJOBS All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form, or by any means electronic or mechanical including photocopying, recording or any information storage and retrieval system without permission in writingfrom SAPTOPJOBS
  • 2. PS Configuration Overview 1. PROJECT SYSTEM STRUCTURE 4 1.1 Define Special Characters for Projects 8 1.2 Define Project Coding Mask 11 1.3 Define Field selection for Work Breakdown Structures 14 1.4 Define Validation 19 1.5 Maintain Substitution 24 2. DEFINE TIME PROFILES 29 2.1 Define Profiles for Time Scales 33 2.2 Define PRT Usage 36 3. ACTIVATE PROJECT MANAGEMENT IN CONTROLLING AREA39 3.1 Maintain Value categories 42 3.2 Unit Costing 45 3.3 Create / Change Planning Profile 49 3.4 Maintain Budget Profile 54 3.5 Define Tolerance Limits 57 3.6 Maintain Progress Version 60 4. SCHEDULING TYPES 63 4.1 Parameters for Network Scheduling 66 4.2 Define Database Selection Profile 69
  • 3. Hello Everyone, A Ware Welcome To You All! We are really excited to offer the complete SAP PS configuration pack to the SAP community. This was a much- awaited pack and we are happy to present that to you… As you are aware that our SAP FICO, PP/QM , SD, MM/WM HR, and PM have already achieved the best selling status and have received lots of accolades and really helped the consultants take their SAP knowledge and career to the next level …I am very confident that PS configuration package will go a step forward and do much more than that………. For those who have been on our list and who have bought from us earlier you all know that we have over-delivered on each of our configuration packs and we want to do the same thing with SAP PS config pack too… For those who have visited our site for the first time I would like to welcome you to our site and promise you that we would do our best to ensure that your life at the clients place would be very comfortable… What I have done here is given you a brief of around 69+ pages of content in PS pack so that you can have a feel of what it would be like in terms of structure. The whole pack is extremely voluminous, step by step guide this is just a feeler… So I hope you enjoy this…. So lets dive right in….
  • 4. 1.Project System Structure Planning of all activities in detail is an essential process in any project irrespective of its size and volume. Right Project planning helps to ensure the completion of project at right time with right amount cost involved. It is also essential to know the amount of resource and funds required to execute the project and also the timings of its requirement. In an organization many tasks like construction, installation of large machinery etc.., are carried out as projects. Project organization is a prime and foremost step in project structuring. Project Organization in PS helps to  Plan the project  Monitor the project progress  Control the project progress Projects can be structured based on  Work Breakdown Structure (WBS) element  Work package – with activities From Finance point of view, each project is identified as  Externally financed project  Internally financed project Project System Organization: -
  • 5. Project system has got the following parameters. Project definition WBS element Networks Activities The above discussed PS module elements are assigned to the existing organizational units. I.e. these are assigned to the existing controlling area, company code, business area, profit center and plant. In short we can say that there is no independent org structure for PS module like SD and MM. The PS parameters are assigned to the existing organizational units at different levels. Let us discuss the possible assignments of each PS elements with existing org. structure. Project Definition: Project Definition is the process of defining the project with its objective, Accounting information and logistic related information. Accounting information:- Controlling Area Company code Business Area Plant Location Profit center Currency Budget profile Interest calculation profile Planning profile Investment profile Result Analysis key
  • 6. Logistic information Network profile WBS Scheduling profile Person responsible Start & End date Factory calendar Time unit WBS Element: - WBS element is a master data used for projects. The usage of WBS is  Organizes the project task in an order  Process planning, cost planning, capacity planning  Costing and controlling  To know the amount of work involved in a project WBS is created with reference to the project definition. The data maintained under project definitions are copied into WBS WBS Accounting information:-  Currency – Copied from projection profile. Can be changed only if company code currency is different from controlling area and there must NOT be any budget, commitments exist for the WBS element.  Company code  Business area  Profit center  Plant
  • 7. Network: - Network represents flow of task in a project. Tasks performed with WBS such as planning, controlling etc. can be done with network also. The structure of the network is similar to that of production order and maintenance order. Network can be assigned to  Project definition  WBS  Time sheet entry Activities: - Activities indicate the sequence of any process. Activities contains Duration Start and finish Requirement of resources Cost requirements Activities can be Internally processed Externally processed Service related General cost activities Now let us see what is there in the configuration for PS structure. The project definition contains various profiles from costing point of view. We shall start from WBS structure.
  • 8. Define Special Characters for Projects BACKGROUND This configuration setting enables to define how the project number is coded for editing. Following parameters are controlled in this setting to edit the project number.  Length of the key for project coding - Max. five  Mandatory length of the project coding – whether all five must be filled or not.  Special characters allowed for entering WBS SCENARIO Define special character for projects. INSTRUCTION Follow the Menu Path: IMGProject System  Structures  Operative Structures Work Breakdown Structures (WBS)  Project Coding Mask  Define Special characters for Projects Click or use OPSK in the command field and press Enter.
  • 9. Maintain fields as explained below Field Name Value and Description of field Length of key for coding of the project definition and WBS elements. Possible entries are E.g.5 indicates maximum It must be set carefully before creating any projects. We will proceed with 1 in our example. Key used to specify project coding and WBS element must of same length as it is defined here. E.g. Leave it blank not to restrict the length of project coding and WBS element. To help entering the WBS element in the work break down structure, this special key is defined. E.g. Enter ". To enter a new WBS element under WBS element, it is enough to enter " and new number. E.g. say new number is 30, then system will maintain the number with all prefixes and the number 30.
  • 10. Special character used to limit the segments in the coding. E.g. / to limit with the character / between the segments. Check in this tick box will allow only the coded project numbers within the project system. E.g. tick the check box. This field is used for automatic number assignment. E.g. Leave it blank. Click Click Impact of this configuration in Master Data / Transaction Project numbering will be as per this project special character setting.
  • 11. Define Project Coding Mask BACKGROUND This configuration setting enables to create masks for editing the project number. Project coding mask is helpful to simplify the complex project numbers. It is also used to indicate the position of the WBS element. SCENARIO Discuss the project coding mask. Ex: /000-XXX-000/XXXX INSTRUCTION Follow the Menu Path: IMGProject System  Structures  Operative Structures Work Breakdown Structures (WBS)  Project Coding Mask  Define Project Coding Mask Click Or Enter OK02 in the command field – press Enter. Click Maintain fields as explained below
  • 12. Field Name Value and Description of field Length of key for coding of the project Note:- Here the project id can be maximum of 1 digit as we have set up the PL field in the above setting as 1. Define the coding mask for project definition 0 (zero) – only numeric characters X – alpha numeric characters Maintain description of coding mask Tick in this check box will not enable the new request for WBS element, project definition or appropriation request to be created with this masking code. Tick in this check box will not allow creating coding mask for standard project or WBS element. Click Click Impact of this configuration in Master Data / Transaction Project coding mask created here will be used while creation project definition, WBS element or appropriate request.
  • 13.
  • 14. Define Field selection for Work Breakdown Structures BACKGROUND This configuration setting enables to define the WBS field selection. Through this configuration setting it is possible to make a field mandatory, optional, hide or view only. It is required to make certain field to make mandatory according to the business requirement. SCENARIO Make Project Description field as mandatory for company code 3000 INSTRUCTIONS Follow the Menu Path: IMGProject System  Structures  Operative Structures Work Breakdown Structures (WBS)  User Interface Settings  Define Field Selection for Work Breakdown Structures Click
  • 15. Double click Double click on Description field
  • 16. Click on Click Enter the company code as “1000” select radio button Double Click to influence any of one fields
  • 17. Click Double click Similarly as explained above, field selection can be done for WBS element also. Note:- the procedure is same for Network field selection as well. Impact of this configuration in Master Data / Transaction
  • 18. When creating project definition CO area become mandatory entry
  • 19. Define Validation BACKGROUND This configuration setting enables to define validation. Use validations to check values and value combinations that users enter in the Project System. Validation can be carried out at various points in time. Following are the steps to be carried-out:  Enter a name for the validation.  The application area is proposed by the system.  Enter a call-up point when the validation should be carried out.  Create a validation step or select an existing one.  Select the field that you want to use for the validation.  Enter a prerequisite and specify how the validation should be carried out.  For each validation step enter a prerequisite, a check and a validation message. The message is issued when the prerequisite is met and when the value does not check. SCENARIO Discuss validation defining. INSTRUCTION
  • 20. Follow the Menu Path: IMGProject System  Structures  Operative Structures Work Breakdown Structures (WBS)  Maintain Validations Click Click the required object to create validation E.g. Click Enter validation name. e.g. ZLEGL02 and text as “check profit center” Click
  • 21. Click to enter any prerequisite Double click Click Click Enter the project definition to which the check is to be applicable. Double Click
  • 22. double click Click Click Enter the value which must be maintained as profit center for project definition with W Click Double Click Enter message type Enter message number. Message variable entered if the message contains any variable. Example: - Message:- "Acount $ is not allowed in company code $" Output field 1: BSEG-HKONT (=400000)
  • 23. Output field 2: BSEG-BUKRS (=0001) Click Message appear at the bottom
  • 24. Maintain Substitution BACKGROUND This configuration setting enables to define substitution. Use substitutions to replace values and value combinations in the Project System. In addition you can define several interdependent substitution statements for future use. Following are the steps to be carried-out:  Enter a name for the Substitution.  The application area is proposed by the system.  Enter a call-up point when the substitution should be carried out.  Create a substitution step or select an existing one.  Select the field that you want to use for the substitution.  Enter a prerequisite and specify how the substitution should be carried out. SCENARIO Discuss substitution defining. INSTRUCTION Follow the Menu Path: IMGProject System  Structures  Operative Structures Work Breakdown Structures (WBS)  Maintain Substitution
  • 25. Click Click on the object where the substitution is to be created. E.g. whether on project definition or on WBS element Click to create rule or click to create substitution Enter substitution key and text Click
  • 26. Enter the step number and text Double click Double click Click Click Enter the finish date Click
  • 27. Double click Click Select the field person responsible Click Select the appropriate radio button. E.g. Click
  • 28. Enter the required value Click
  • 29. 2.Define Time Profiles BACKGROUND This configuration setting enables to define the time profiles. Time profile is used to specify various working time periods used in the project planning board. Time profile contains the evaluation period and planning period. Evaluation period is the time frame for working with and displaying data in the project planning board. Beyond the evaluation period, it is not possible to work with and display the data in the planning board. Planning period is used to define the time frame for carrying out current planning in the project planning board.  If the start date is beyond the current date, the planning period begins with the start date. If the start date is earlier than the current date, the planning period begins with the current date. SCENARIO Discuss the time profile. INSTRUCTION Follow the Menu Path: IMGProject System  Structures  Project Planning Board  Define Time Profiles Click
  • 30. Click Maintain fields as explained below Field Name Value and Description of field Key identifying the time profile. Enter key and description. E.g. Key indicates the type of entry to be made. I.e. Monthly, yearly. Select from available entries
  • 31. for evaluation period E.g. L to indicate years Enter start date. E.g. 0. Indicates start from 0 years Start date is the date of the first day of the period to which the data required to be evaluated. System determines the first date with entry here along with entry type. E.g. today is 14.01.2005 Type of entry: G Start: -10 Finish : +20 evaluation period. For This generates an evaluation period from 04.01.2005 to the 03.02.2005. Enter finish date. E.g. 2 indicates evaluation allowed for next two years. Similarly maintain the entries as shown below for planning period.
  • 32. Click Click Click Impact of this configuration in Master Data / Transaction Time profile defined here can be assigned to the project planning board in the subsequent settings.
  • 33. Define Profiles for Time Scales BACKGROUND This configuration setting enables to define Time scale profile. Time scale profile defines the properties of all possible scales. The possible time scale headings are  Yearly split  Quarterly split  Monthly split  Weekly split  Daily split  Hourly split  Minute split  Shift split For each time scale heading maximum and minimum time scale must be maintained. SCENARIO Discuss the profile for time scale. INSTRUCTION Follow the Menu Path: IMGProject System  Structures  Project Planning Board  Define Profiles for Time Scales Click
  • 34. Click to create new entries. Note:- it is always suggested to copy from the existing standard entry. Select any standard row. E.g. second row Click Enter the new time scale profile. E.g. ZPS_PROAAA
  • 35. As the standard setting is sufficient nothing much to change other than specifying the bar chart width in mm for minimum and maximum. Click Click Click Impact of this configuration in Master Data / Transaction Profile for time scale defined here will be used in the project planning board setting.
  • 36. Define PRT Usage BACKGROUND This configuration setting enables to define the PRT usage. Production Resource Usage controls the usage of PRT in different task list and applications. It is possible to allow the usage of PRT only in networks. SCENARIO Discuss the PRT usage setting. INSTRUCTION Follow the Menu Path: IMGProject System  Production Resource Tool  General Data  Define PRT Usage Click
  • 37. Click to create new entries, SAP standard usage is sufficient to work with. Let us discuss the standard usage 003. Select usage 003 Double Click in the left side
  • 38. Maintain the task list type under the usage. Click Click Click Impact of this configuration in Master Data / Transaction When creating the PRT, usage can be defined as per the settings here.
  • 39. 3.Activate Project Management in Controlling Area BACKGROUND This configuration setting enables to activate project management in controlling area. This setting also enables to activate the commitment management for a controlling area. SCENARIO Discuss activation of project management in controlling area. INSTRUCTIONS Follow the Menu Path:- IMGProject System  Costs  Activate Project Management in Controlling Area Click
  • 40. Available controlling areas are displayed at right side. Select the desired row To the desired controlling area activate the projects( ) and commitments management ( )
  • 41. Note:- There could be other settings related to CO module, like assigning the company code to controlling area etc.. but here the point of activating project management only explained. Click
  • 42. Maintain Value categories BACKGROUND This configuration setting enables to define value categories. Value categories are required for  Updating project information database  Calculating interest on projects  Defining reports  Updating quantities in project info. SCENARIO Discuss maintenance of value categories. INSTRUCTIONS Follow the Menu Path:- IMGProject System  Costs  Value Categories  Maintain Value categories Click Enter the controlling area Click Click
  • 43. Enter the value category. E.g. Z01 Enter the description for value category maintained. Select the relevant radio button as explained below. E.g. Cost radio button to the purpose of posting of costs or outgoing payments. Revenues to the purpose of posting revenues and incoming payments SKFw.Tt to the purpose of posting statistical key figure with total characteristic value SKF FVA to the purpose of posting statistical key figure with fixed value characteristic
  • 44. Click
  • 45. Unit Costing Unit costing will be where you have information on sources of supply, quantities, and prices. Plan overall or annual values for unit costing. Costing variant is to combine all the controlling parameters for costing. Costing variant represents the link between the application and customizing because all costing run must reference a costing variant as they are made and stored. The costing variant controls the following parameter.  Costing variant contains the valuation variant and costing type.  Valuation variant controls price to pickup for material, subcontracting and external processing.  Valuation variant contains the costing sheet also (over head calculation) BACKGROUND This configuration setting enables to define the variants for Unit costing. SCENARIO Define / discuss costing to create variant. INSTRUCTIONS Follow the Menu Path:- IMGProject System  Costs  Manual cost planning in WBS  Unit Costing  Create Costing Variant. Or Enter OKKT in the command field – press Enter.
  • 46. Maintain the fields as explained below Field Description This field sets how the cost to be estimated based on the materials, Production orders with controlling, Internal orders and sales orders. Based on the type of business scenario costing variant is created. Click on new entries
  • 47. In Control Tab maintain the field as explained below Field Description This field requires how the cost estimate to be used. Ex: unit cost est. for proj This field specifies the prices the system selects to valuate the quantity structure of a cost estimate with quantity structure or of the order, or to valuate the costing items of a unit cost estimate. Ex: Planned valuation –orders. This field sets how the date control of a cost estimate is handled. Ex: Mod.std cost est. dates
  • 48. Click on the assignment tab Click on to verify the variant. To verify the variant – variant to be saved. Click Save . If the Variant is ok – system will give message Impact of this configuration in Master Data / Transaction Based on the business scenario use the costing variant
  • 49. Create / Change Planning Profile BACKGROUND This configuration setting enables to create / change planning profile. Planning profile is required to plan the cost methods. Following controls are available in the planning profile. Time frame – can specify which values are the to planned and their fiscal years. Value display - to display the decimal places and decimal factor Detail planning – values for cost element planning ,activity Input planning and cost planning. Planning profile is used  For all WBS elements or only on planning elements ,  Bottom-Up planning within hierarchical planning ,  Automatic revenue planning. Based on the settings one can decide whether the system updates plan revenues on the corresponding billing elements. Profile can be Cost planning for investment programs or investment measures, and for appropriation requests. SCENARIO Define / Discuss Planning profile. INSTRUCTIONS
  • 50. Follow the Menu Path:- IMGProject System  Costs  Planned Costs  Manual cost planning in WBS  Hierarchical Cost Planning  Create / Change Planning Profile. Or Enter OPSB in the command field – press Enter. Click on the new entries or copy the existing plan based on the business scenario. Maintain the fields as explained below Field Description This sets the control parameter for the planning. In the Manual Planning - when the Bottom up planning indicator is set, the system automatically carries out the total up function in structure planning for costs and revenues each time you save and check data. The structure plan value for the higher level WBS item is the total of all the plan values for the WBS elements directly below it. To ensure that the structure plan values for the whole project structure are uniform, must access the structure planning for the whole project and check and save the values.
  • 51. This field sets cost planning is possible in only those WBS elements are defined as Planning elements. Can carry the cost planning in any WBS elements when the indicator is set. This field require the time frame in future – means how far can far. Based on the scenario can mention Past and start time frames. This field sets the values required in total and annual years. This field sets whether any decimal places and its scaling factor required for the planning profile. This field sets the cost element group as primary costs where goods brought in externally like raw materials , operating supplies , services ,etc based on the chart of accounts. Ex: OAS_PRIM This field sets to summarize cost elements of the same types in reports. Ex: OAS_REVEN This field specifies the cost center group of sender for which activity types are planned. EX: H1400 This field sets each activity type in this group can appear
  • 52. as a sender activity type in activity input planning. EX:A1 This field sets a group of stastical key figure used in reporting to process multiple key figures in a single transaction. EX: STAT_9000 This field sets how the cost estimate is performed and valuated. EX: INV1 This field sets the exchange rate in the system and value dates determines daily exchange rates applies For currency translation. EX: 001 This field sets the types of planning currency based on Controlling areacurrency / object currency / Translation currency. EX: Controlling area currency. This field sets how the revenue planning should happen automatically through quotation or sales order.. This field requires to enter the type of revenue element for billing plan to WBS element.
  • 53. Click Save . Impact of this configuration in Master Data / Transaction Based on the planning profile – one can carry out Cost Planning by entering values in the cost plan column using CJ30 transaction code.
  • 54. Maintain Budget Profile BACKGROUND This configuration setting enables to control the budget for the Project. SCENARIO Define / Discuss budget profile. INSTRUCTIONS Follow the Menu Path:- IMGProject System  Costs  Budget  Maintain Budget Profiles. Or Enter OPS9 in the command field – press Enter. Click on new entries or copy the existing profile based on the Business scenario. Maintain fields as explained below Field Description This field sets type profile type and description. Ex: 1000 This field sets the time frames which can in past, future or start and enable total and annual values. Ex: enable in Future - 3 This field sets WBS element using this budget profile can
  • 55. only be budgeted if the WBS element or a WBS element above it in the hierarchy is assigned to a program position ofan investment program with the correct program type. Ex: 1000. This field sets type of control that should be available while budgeting and how the activation type should be. i.e Automatic activation during budget allocation. EX : 1 –means automatic allocation during budget activation. This field sets a WBS element using this budget profile can only be budgeted if the WBS element or a WBS element above it in the hierarchy is assigned to a program position ofan investment program with the correct program type. Ex: 1000. Based on the type of business scenario use the control parameters for network scheduling Click Save . Impact of this configuration in Master Data / Transaction Based on the business scenario define and use the control parameters.
  • 56.
  • 57. Define Tolerance Limits BACKGROUND This configuration setting enables to give tolerance limit for the budget profile. The Tolerance range /limits the budget if any project overruns the allocated cost / money. Activate availability control for a certain budget profile. Can specify one or more tolerance limits for each activity group for a budget profile. Selected actions (warning, warning with mail to person responsible for project, error message) are triggered when these limits are reached. Tolerance limit for all activity groups can be chosen as activity group ++ which make entry easier. Tolerance limit for all activity groups can be used if it is not required to define a separate tolerance limit for each activity group. It is possible to define a limit for a specific activity group in addition to a tolerance limit defined for all activity groups. This additional tolerance limit has priority over the generally valid tolerance limit. SCENARIO Define / Discuss Tolerance limits. INSTRUCTIONS Follow the Menu Path:- IMGProject System  Costs  Budget  Define Tolerance Limits.
  • 58. Click on new entries if the controlling area belong to the Controlling does not exists. If exists define the tolerance limits. Field Description This field tells about the controlling area. Ex: 2000 This field sets the budget profile to the controlling area. Ex: 1000 This field tells about target group of the activity type. Ex: ++ indicates that target group belongs to all activity types. This field sets activity type. Ex: 1 /2 / 3. This field sets how much the usage should be for the said budget profile. This field tells about difference between the assigned funds and the budget exceeds the absolute variance, availability control triggers the appropriate action. This field tells about the controlling area currency. Click Save .
  • 59. Impact of this configuration in Master Data / Transaction Based on the business scenario define the budget tolerance limits.
  • 60. Maintain Progress Version BACKGROUND This configuration setting enables to define the progress version. Progress version is required to create control data for calculating the % of completion and the earned value. Note:- This is to be done in discussion with CO team SCENARIO Discuss progress version . INSTRUCTIONS Follow the Menu Path:- IMGProject System  Progress  Progress Analysis  Maintain Progress Version Click Click to create new entry
  • 61. Maintain the fields as explained below Field Description Key identifying the controlling area. Enter controlling area Key identifying the progress version. Enter progress version and description Key identifying the plan version. Note:- the CO version must have exclusive use 03 i.e. earned value analysis. Earned value is calculated by applying the % of completion of the cost amount. This defines which cost amount is to be used. Available entries are
  • 62. Value used for weighting in the aggregation of the % of completion. Possible entries are Key identifying the type of planning to be used. Available entries are This key to determine whether either:  the earliest date is set to the latest date of the activity or  The latest date is set to the earliest date of the activity. Tick in this check box will enable the system to use the system uses an existing method if the method is not maintained. Click
  • 63. 4.Scheduling Types BACKGROUND This configuration setting enables to define the scheduling types to the projects. Scheduling types governs the way scheduling is to be performed. SCENARIO Define / Discuss scheduling types. INSTRUCTIONS Follow the Menu Path:- IMGProject System  Dates  Scheduling  Define scheduling types. Or Enter OPJN in the command field – press Enter.
  • 64. Field Description This indicator sets the scheduling type as Forward for orders and Networks means schedules from the start date. This indicator sets the scheduling type as backward for orders and Networks – means schedules from the Finish date. This indicator sets the capacity requirements to calculate. Distributed across the periods based on the types
  • 65. of dates. This indicator sets as today’s date for scheduling. This indicator sets the time to enter the basic dates for the production orders. Based on the type of business scenario use the scheduling type. Click Save . Impact of this configuration in Transaction When performing the scheduling in the project, scheduling will be carried out as per the setting maintained here.
  • 66. Parameters for Network Scheduling BACKGROUND This configuration setting enables to define parameter for network scheduling. Network scheduling contains settings for  Dates adjustment  Type scheduling to be performed  Control to allow start day in the past  Reduction type This setting is performed for the combination of Plant, order type and Production scheduler. SCENARIO Define / Discuss control parameters of scheduling. INSTRUCTIONS Follow the Menu Path:- IMGProject System  Dates  Scheduling  Specify Parameters for Network scheduling. Or Enter OPU6 in the command field – press Enter.
  • 67. Field Description Key identifying the plant. E.g. 1000 Key identifying order type. E.g. PS05 Key identifying the production scheduler. E.g. * This control determination of basic dates to the element or to its dependant requirements during lead time scheduling. Type of scheduling to be applied to this order type or network type.
  • 68. Indicates whether the past start date is allowed. If it is to be allowed, enter the number of days. E.g. Leave it blank. Tick in this check box automatically schedule the network on saving. Tick in this check box displays scheduling log automatically during each scheduling e.g. Leave it blank Tick in this check box considers the exact time of break during scheduling. e.g. Leave it blank Tick in this check boxwill not consider the partially confirmed operations. E.g. Leave it blank This tick mark to schedule the component on latest scheduled date. Indicates what reduction type is to be employed Number of reduction level to be applied. Click Save Impact of this configuration in Master Data / Transaction During network creation, scheduling will be done according to the settings maintained here.
  • 69. Define Database Selection Profile BACKGROUND This configuration setting enables to define Database selection profile. This is the process of picking up the desired objects and fields from the database for information analysis purpose. Note: - Standard SAP setting will be sufficient in most of the cases. Let us discuss the standard setting and understand. SCENARIO Discuss the Database selection profile. INSTRUCTION Follow the Menu Path: IMGProject System Information system  Selection  Define Database Selection Profile Click
  • 70.
  • 71. Field Name Value and Description of field Tick in this check box will enable only last person who made changes only to make further changes Tick in this check box will pickup its superior objects also. E.g. WBS elements are selected as objects, but it will pickup its project definition also. Changes can be made only through the configuration setting if this check box is ticked. Tick in this check box will pickup project definition from the database If not ticked, project can not be made as a selection criteria as project definition does not appear in the selection screen. Tick in this check box will pickup sales order and customer quotation for selection
  • 72. Tick in this check box will pickup material component from Database. Tick in this check box will pickup WBS element Tick in this check box will pickup hierarchy of sub element of WBS. Tick in this check box will stipulate network and orders assigned to WBS. Tick in this check box will pickup network assigned to WBS element Tick in this check box will pickup the production order, process orders assigned to WBS Similarly all check boxes which are ticked are selected from the data base. Click Click Impact of this configuration in Master Data / Transaction Information system when displaying the objects, it will pickup data from database as per the configuration maintained here. That’s it then… The entire PS configuration pack comes in 7 voluminous power packed CDS f u l l o f m e a t y c o n te nt and each sub module in SAP PS is broken into Configuration, End user and Power point. There are tons of bonuses which you get along with this pack including complete Integration documents, PS Interview questions and answers and a boatload of step by step guides……… You can take advantage of the special offer by visiting the site at http://www.sap-topjobs.com/SpecialPP/sapps20071123.html
  • 73. All our packs are shipped thru FedEx and reaches you in three days time. One more thing this configuration pack is compatible with version 4.7, version 5.0 and 6.0 So you really do have to worry about the version at all.. We have taken care of that… Also all future version changes will be provided as free updates to you. So you can sit back relax and play the music …. What I want from you now is to do yourself a favour by bringing the brains and wisdom of SAP PS Experts with more than 12+yrs of implementation experience to your drawing room today. Do it right now my dear friend and take your SAP career to the next level…. You will love it I promise you…. http://www.sap-topjobs.com/SpecialPP/sapps20071123.html www.sap-topjobs.com