SAP MRP Configuration
Activating MRP and Planning File Entry
a) Activating SAP's Material Requirements Planning (MRP)
This configuration allows you to choose the plant for which you would want to activate SAP Material
Requirement Planning (SAP MRP). Activating MRP for the plant allows one to use the SAP MRP tool
for the plant. SAP Transaction code OMDU and the SAP path is Logistics > Production > MRP >
Planning File Entry > Activate MRP and Set up Planning File
b) Activating Planning File Entries for a Plant
Activating Planning file entry for the plant (through a variant that can be rescheduled) allows you to
collect all the material in a planning file list, which has an MRP Type in the material master MRP 1
View (other than MRP Type XO)
The process of recording a planning file entry for a material, can be run periodically using a batch job
scheduling method. The transaction code to set up the variant and period scheduling is OMDO and
the Path for activating the planning file set up is Logistics > Production > MRP > Planning File Entry >
Activate MRP and Set up Planning File
All the entries in the planning file will have a “change indicator” specifying that a material has
undergone a change (change in receipts elements or issues elements). This indicator will help you to
choose only those materials that have undergone a change, through the use of planning key called
“Net Change Planning” when running MRP.
The planning file record for a material also has a “net change planning in the current horizon” field
which will be set if the change in the materials receipt or issue element is valid in the planning
horizon. This indicator will help you choose only those materials which have undergone a change in
the planning horizon; through the use of a planning key, in an MRP run, called “Net change planning
in the planning horizon”.
Plant Level configuration for MRP
Plant Level configuration for MRP
SAP MRP is run at plant level or at a group of plant level (called as scope of planning), thus the MRP
configuration is done at Plant level.
The configuration done for SAP MRP at Plant level would also be true for SAP Consumption Based
Planning (SAP CBP) settings.
Transaction code OPPQ takes you in to the SAP MRP configuration called as – Plant Parameters for
Material Requirement Planning. The Path which can be used is Logistics > Production > Material
Requirement Planning > Plant Parameters > Carry out Overall Maintenance of Plant Parameters.
The Transaction code for Consumption Based planning is OMI8 and the Path is Logistics > Materials
Management > Consumption Based Planning > Plant Parameters > Carry out Overall Maintenance of
Plant Parameters.
Fig MRP - Config 1
In the transaction code for Plant level parameters for SAP MRP, you should first input the plant and
press the maintain button.
If you have already maintained the configuration for the parameters, then it states so, if you haven’t
then it simply says – “To Maintain” next to the parameter
Fig MRP - Config 2
Following are the parameters that need to maintain as a part of SAP MRP/CBP Configuration:
a) Number ranges
The number range ID’s are maintained for the following objects:
the Planned orders
the reservations,
the dependent requirements,
the simulative dependent requirements,
the purchase requisitions,
the MRP Lists,
In this section only the number range ID’s are maintained. While the actual number range is
configured, for the number range ID, using a transaction code OMI2 (for the above mentioned objects
created in the planning run). One can also use the transaction code OMI3 for the objects created
manually in the front end.
Every number range interval, created using OMI2 and OM13, has an ID, which can be allocated to
the objects at plant level, i.e., every plant can have a different number range for the objects
mentioned above.
b) Availability Check rule for Backorder Processing
As per standard SAP, the Availability checking rule for the backorder processing is “PP”, though you
can have your own availability check rules created or configured.
Every Availability checks rule (availability checking scope defined) has a set of receipts (Purchase
orders, Production orders) and issues (Sales orders, dependent requirements, reservations, planned
independent requirements etc) which are to be considered or not to be considered during the SAP
availability checks.
To have the checking rule work along with the configuration, you should have the Availability
checking groups maintained in the material master. The Checking groups are configured to be
associated with the checking rules (checking scopes).
The availability checking rule (checking rule scope) has to be maintained, for a given SAP
functionality and it has to be assigned to the availability checking group maintained in the material
master. The SAP functionalities that use availability checks to check the availability of the header
materials as well as components at the plant at the time of sales order creation, the availability
checks of the header material at the time of sales order delivery, the availability checks for
components in production – thus reporting the missing parts list, the backorder processing etc.
c) Reporting
This configuration is used for the following purposes.
• To configure the objects, which are to be considered in the calculation of the “receipts days
supply” like the production orders/process orders, firmed planned orders, purchase orders,
assigned planned orders, firmed purchase requisitions, QM Inspection lots, reservations, safety
stocks
• To configure the reporting of “periods totals” in terms of a defined period (day, week, month,
periods as per planning calendar) of in Stock requirement list, MRP list, simulative MPR or
interactive MRP
d) MRP Controllers
This is a mandatory configuration. Here you can configure the list of MRP controllers for the plant. A
MRP Controller is a person or a group of people, which is responsible for planning a material or a
given list of materials.
You have to assign the MRP controller to the Material Master MRP 1 View, so as to delegate the
responsibility of the planning and evaluation of planning for that material.
e) Floats
Floats are buffers in the total lead time, that are provided in production/process order or in the
planned orders created manually or during an MRP run. The schedule margin key is used in the
Material Master MRP 2 View. It is used in MRP as well as in production order.
The floats are defined using the scheduling margin key.
Opening period: Number of working days between the date that the order is created and the planned
start date. This time is available for the MRP controller to convert a planned order into a purchase
requisition or a production order.
Float after production: Number of working days between the scheduled finish date and the order
finish date; used as a float in production scheduling.
Float before production: Number of working days between the order start date and the scheduled
start date; used as a float in production.
Scheduling release period: Number of workdays between the planned start date and the date for
releasing the order. If the order release indicator is set, the production order is released by a
background program that takes all dates into account.
Plant Plant
Name
Margin
Key
Opening Period
(In Days)
Fl. Before Production
(In Days)
Fl. After Production
(In Days)
Release Period
(In Days)
0001 0001 001 5 2 2 5
0001 0001 002 5 3 3 5
0001 0001 002 5 4 4 5
f) Special Procurement
The special procurement function helps you to configure and assign special procurement to the
materials which can be used during an MRP run while creating the procurement proposal.
The special procurement functions are withdrawal from alternate plant, production in alternate plant,
subcontracting, direct production, phantom item planning,
https://sites.google.com/site/sapswords/home/learn-sap-pp/sap-material-master/sap-mrp2-view
Example: For Stock Transfer from Plant C001 to Plant C002
Create the Special procurement key (Key number = 12 as an example) in the plant C002 with the
procurement type as “F” and special procurement as “U” (Stock transfer) and the special procurement
plant as “C001”. Normally when creating the special procurement key use Z, Y or X to the Key
number, so instead of having Key number as 12, we could have something like Z2 or YA etc.
Fig MRP - Config 3
Similarly for Withdrawal from Alternate plant, you could have a Configuration as below:
Fig MRP - Config 4
Similarly for Subcontracting, you could have a Configuration as below:
Fig MRP - Config 5
Similarly for Production in alternate plant, you could have a Configuration as below:
Fig MRP - Config 6
g) Conversion for Planned orders
In this configuration parameter, you can maintain the production order type or the process order type,
which the system should use as default during the planned order conversion. Setting defaults in the
plant parameters configuration allows the system to fix and select the order type for a plant during the
conversion process.
Note: This can be a useful tool when you are using one production order type and one process order
type, but if you are using multiple production/process order types, then you should not be maintaining
defaults here.
Also for the purchase requisition conversion, you are given an option in the configuration to define the
maximum number of planned orders that can be converted in to Purchase requisition.
Fig MRP - Config 7
g) Dependent Requirements availability check
When carrying out the availability check for each of the components in a MRP BOM explosion, the
system needs to know the availability checking scope rule. Again we would maintain the standard
Checking rule as PP or you could alternatively configure one for yourselves.
h) BOM/Routing Selection ID
This configuration parameter is really important and it is mandatory to maintain one, since it helps
selection of BOM and task lists in the planned orders. Though there is one more place in the planned
order Scheduling parameters MRP configuration, where you can maintain the selection ID for
selection of the Task lists (Routing/Recipe/Rate Routing).
A selection procedure is set to select BOM or Routing/Recipe on priorities set for the BOM usage or
for the task list types and the task list status. Knowing the selection procedures allows the MRP run to
select the right BOM and task list for the planned orders.
In other words, you could have the BOM Selection being set for selection of the Production BOM
Usage first and if a BOM for the material with the Usage – production (Usage = 1), is not found, you
could have the system search for a BOM of universal Usage (Usage = 3).
Similarly, you could have a task list of type Routing or Recipe or reference operation sets selected
and set in priorities of selection (1st – Routing, 2nd – Reference operation sets, 3rd, which has a Status
Released for all purposes or released for costing) etc.
h) Scheduling of Planned orders
This configuration parameter is really important and it is mandatory to maintain one. It allows you to
set the control parameters for scheduling of planned orders of type LA at a given plant and for a given
MRP Controller. You can leave the MRP controller as “*” to have the scheduling parameters true for
all the planned orders across all the MRP controllers.
The following control parameters can be configured here:
 The Routing/Recipe Selection ID, specifying the routing/recipe that would be selected for
detailed scheduling, as per the priorities set for task list type and task list status.
 The Detailed scheduling, using the task list is only carried for the scheduling
Horizon mentioned, i.e., if the planned orders dates lie beyond the scheduling horizon, then the
basic date scheduling is used where the in house production times from the material master is
used.
 Allow Scheduling Indicator allows the planned orders to be scheduled using the detailed
scheduling or basic date scheduling, either of the two, depending upon the availability of the task
list and scheduling type selected for the MRP run.
 Generate Capacity requirements indicator allows generation of the capacity requirements
for the work centers and loads them accordingly. The loading of the work centers is as per the use
of the work center determined through the scheduling carried out.
 The Task list selection, scheduling horizon, scheduling indicator and the capacity indicator can
also be set for rough cut planning used for Long term planning purposes.
 The next configuration parameter talks about the configuration of the selection of the type of
scheduling level that should be used for adjusting the basic dates of planned orders. The various
options available are rate based scheduling, lead time scheduling, scheduling using takt times.
 The Adjust planned order dates configuration option allows you to readjust the scheduling
results or the basic dates every time you carry out Scheduling. Though there is one more
scheduling configuration option provided by the system for overwriting/adjusting the existing basic
dates by the new dates arrived at, through rescheduling (using the scheduling level as
mentioned).
The system not only offers an option to adjust the basic dates for the planned order arrived at by
using the scheduling level set, but it also setting the dates of the dependent requirements to the
operation start date or the order start date.
This configuration not only adjusts or sets the dates of the header planned order and the
dependent planned orders, but it also generates capacity requirements for the same.
See below for the details of adjusting dates in scheduling and adjusting dates for capacity
requirement generation:
 You can adjust the Basic Dates of the header planned order using the scheduling level
and adjust (or set) the dependent requirements to the start of the header planned order
 You can adjust the Basic Dates of the header planned order using the scheduling level
and adjust (or set) the dependent requirements to the start of the respective operation to
which the dependent requirements are assigned to
 You can decide not to adjust the Basic Dates of the header planned order arrived at by
using the scheduling level and at the same time not-adjust (or not set) the dependent
requirements to the start of the header planned order
 You can decide not to adjust the Basic Dates of the header planned order arrived at by
using the scheduling level and at the same time not-adjust (not set) the dependent
requirements to the start of the respective operations to which the dependent requirements
are assigned to
 You are also provided an option to configure the scheduling type – whether forward or
backward scheduling. It is a normal behavior for the standard system to have this configured as
“backward scheduling” so that SAP MRP (material requirement planning) never misses the
customer delivery date or order availability date. An option is also provided to not-to-schedule, any
orders during the breaks set in the factory calendar.
 Start date in the in the past options allows you to push the start date of the planned orders
to a certain number of days in past. If the order start date goes beyond the number of days
allowed, then the system uses the concept of ‘today’s scheduling” and sets the start date of the
planned order to today’s date and carrying out forward scheduling there-after.
 One of the scheduling parameters is “reduction measures”, used to reduce the total order lead
time in circumstances designed. You can avoid configuration of reduction measures, if you are not
using it.
Fig MRP - Config 8
i) Default Values for External Processing
For external purchasing, one can maintain the default lead time required for conversion of Purchase
requisition into purchase order, using the planned delivery lead times from the purchase info record or
purchasing agreement. So as to use the planned delivery times from the purchase info record, one
should also maintain the source list for the material, with the same vendor in the source list and the
purchase info record.
Using the planned delivery times from the material master or from purchase info record, is totally a
decision of the consultant. It is indeed a nice additional option provided by SAP for using the lead
time from info records.
j) Planning Horizon
Maintaining a planning horizon helps the system to plan only those demands, which fall in the
planning horizon starting from today. When an MRP Run is taken, the planning horizon is number of
work days as mentioned (let’s say 180 days) from today’s date; the system would not plan any orders
whose start date lies beyond this horizon.
k) Available stock for net requirement calculations
SAP MRP offers you a choice to select the most controversial stock types, in its net requirement
calculations. The stock types are – stock in transfer (stock in transfer is considered as stock at the
receiving plant as it is already issued from the sending plant), blocked stock, restricted batch stock
(stock of batches marked with restricted batch)
Fig MRP - Config 9
l) Option to trigger direct Production in MRP or in production planning
j) Allowing start date in the past
MRP Group Level configuration for MRP
MRP Group Level configuration for MRP
The entire configuration that is created as a part of SAP MRP Plant level parameter in the above
steps can be also set for an MRP Group. You can group materials using MRP Groups. Each of the
MRP Group can have its own MRP Parameter set. You can set the MRP group in the material master
MRP 1 View.
MRP Group can be maintained using transaction code OPPR or the transaction path – Logistics >
Production > MRP > MRP Groups >
Advantage of working with MRP Groups:
Working with MRP groups can be convenient for a plant or an organization, since by assigning the
MRP groups to a set of materials, would allow planner to configure these materials (through MRP
Groups) to behave in a certain manner for planning purposes. In other words, all the materials in the
group would then have a unique planning method or unique planning features. Thus the organization
can device multiple MRP groups with their own planning features and characteristics rather than
having one set of planning features set at the plant level. The group could have its own unique:
Strategy group,
Conversion order types,
Planning horizon,
Planning time fence and roll forward periods,
BOM and task list selection ID’s,
Direct procurement parameters,
Planned order scheduling parameters,
Start number of days allowed in the past
Availability checking groups,
Strategy Groups
The strategy groups can be set for a given MRP group at a given plant. The strategy group consists
of a number of planning strategies assigned in a sequence of priorities. In other words, the strategy
groups, groups together the relevant planning strategies of a material. If you don’t see the default
strategy groups, then we would have to manually maintain the strategy groups on the materials MRP
3 view. Defaulting the strategy groups is a nice idea when the strategy groups would remain the same
across all the materials which would be assigned with a given strategy group.
For example:
A material can have the priority 1 strategy as Made-to-Stock (planning strategy 40) and then priority 2
planning strategy as Made-to-Order (planning strategy 20). Assigning this “strategy group” for a MRP
group in the MRP Group Parameters configuration and then subsequently assigning the MRP Group
to the material master would make the material work on a planning strategy 40 and planning strategy
20 in a sequence of priority.
The primary strategy for the material is 40 – Made-to-stock while the secondary strategy is 20 –
Made-to-order, which means that every time you plan or produce a material or create a sales order
for the material it will always primarily work as a made-to-stock material. Nevertheless, you can also
make to material work as a made-to-order material, by changing the requirement type – “KE” of the
material in the sales order procurement tab, to suit for made-to-order, which the system would allow
since the material’s secondary planning strategy is made-to-order.
Configuring SAP MRP Types
Configuration of SAP MRP Types
In all probabilities, MRP Types is not something which one should configure in SAP; it is used as a
standard configuration. Nevertheless, a consultant should know the importance of MRP types and the
involved pre-configured parameters.
Fig MRP - Config 10
a) MRP Procedures
MRP Procedures defines the type of MRP to be used – Reorder point planning methods, Material
requirement planning or demand based planning methods, Forecast based planning methods, Time
phased planning methods, MPS and the no planning procedures to mark a material with a MRP types
that does not plan a material at all.
b) Firming Type
In the category of MRP procedure called – MRP or demand based planning method and MPS, SAP
offers 8 different MRP types with Firming namely P1, P2, P3, P4 and M0, M1, M2, M3, M4.
When working with the planning time fence, one needs to set the firming methods & the scheduling
methods of the procurement proposals within the planning time fence.
0 1 2 3 4
Firming type
MRP Types
M0 P1
M1
P2
M2
P3
M3
P4
M4
Firming Methods for Procurement Proposals in the Planning time fence
No Firming of Procurement Proposals within the
planning time fence
X
Automatic Firming of Procurement Proposals within the
planning time fence
X X
Manual Firming of Procurement within the planning time
fence (No Automatic Firming of the procurement
proposals )
X X
Treatment with New Order Proposals in the Planning time Fence
Automatic Creation of New Procurement Proposals to
cover the shortages within the planning time fence. But
the dates of these new Procurement Proposals are pushed
outside the planning time fence
X X
No New Procurement Proposals created to Cover the
material shortages within the planning time fence
X X
c) Include External Requirements
The inclusion of external requirements in net requirement calculations is available to be set, when you
are working with reorder point planning based MRP types. Actually there are 2 options in this field,
i.e., include external requirements in the total planning horizon or restrict the inclusion of the external
requirements only within the replenishment lead time.
For example:
If the external requirements are set to be considered in the total horizon (of 7 weeks) then in the
today’s MRP run, the Customer demand will be considered as it falls in the planning horizon and it will
reduce the warehouse stock proportionately which would trigger the reorder point planning
procurement once the stock falls below the reorder point.
If the external requirements are set to be considered in the Replenishment lead time, let’s say the
Replenishment lead time is 1 week, then in that case, only in a MRP run triggered one week before
the start date of the external demand, this customer demand will be considered, thus triggering
reduction in warehouse stocks.
Fig MRP - Config 11
SAP also offers an option to select the additional external requirements that should also be included
in the net requirement planning calculations like the - components supplied to the vendor in a
subcontracting case, reservations set for the components in a production order, reservations of
components in plant maintenance orders, requirements to satisfy the Stock transfer order to another
plant, stock transfer requisitions created for Stock transfer orders, requirements raised because of
stock transfer delivery schedules.
c) Forecasting for MRP
Forecasting MRP Types have a “forecasting indicator” as obligatory, unlike other MRP types which
normally have the forecasting indicator set to optional.
Also the historical data is updated in the material master as total consumption (planned
consumption plus unplanned consumption) or unplanned consumption. When the consumption is
planned as per the MRP reservations, planned consumption is updated and when the consumption is
not planned as per the reservation or is greater than the reservation quantities, then unplanned
consumption is updated.
In MRP type configuration, you have an option of choosing the type of historical consumption of a
material to be used for planning whether total consumption (planned + unplanned consumption) or
unplanned consumption.
After choosing the historical date type, you should configure, the type of forecast requirements to be
considered in MRP planning run, whether total consumption (planned + unplanned consumption) or
unplanned consumption.
The reduction method for forecast requirements is also configurable. The default is reduction by
consumption.
d) Planning method
The MRP type offers you to plan the materials in an external system, like the MRP Type X0. The
indicator called the planning method allows you to choose external planning so as to plan materials in
the external system.
e) Automatic Calculations
You can have the safety stock and the reorder point calculated automatically by the system, when
you are using the automatic reorder point planning methods. In the automatic calculations the system
uses the forecast data.
Configuring SAP MRP Scope of Planning for the Total Planning Run
Configuring SAP MRP Scope of Planning for the Total Planning Run
SAP provides an option to plan multiple plants together or multiple MRP areas in one planning run in
a sequence. Transaction code OM0E can be used for configuration or the logical SAP path – SAP
Customizing Implementation Guide > Production > MRP > Planning > Define Scope of Planning for
Total Planning, can be used to configure.
Step 1 – Define the Name of the Scope of planning run
Step 2 – Define the plants or MRP areas to be included in the planning run arranged in a sequence.
The sequence is defined by the first field called
Configuring SAP MRP Planning time fence and Roll Forward Period
Configuring SAP MRP Planning time fence and Roll Forward Period
The transaction path to configure the planning time fence and roll forward period is: SAP Customizing
Implementation Guide > Production > Material Requirements Planning > Planning > MRP Areas >
MRP Calculation > Define Planning Time Fence and Roll Forward Period
Planning Time Fence:
The planning time fence is the number of work days, within which you can protect the master plan (or
in other words the procurement proposals of a master plan) from being disturbed or changed from
any automatic changes (of an MRP Run). The procurement proposals are firmed so as to protect
them from any changes. The firming of the procurement proposals (planned orders, purchase
requisitions, delivery schedules) in the planning time fence prevents the proposals in the time fence
from being adopted in the next planning run.
In other words, in the planning time fence, the system does not create or delete any procurement
proposals nor does it changes the existing proposals.
The system calculates the time fence from today’s date plus the “number of days mentioned as
planning time fence” in the material master or in the MRP configuration (where you can define the
planning time fence for plant or for a given MRP group). It is needless to say that any new
requirements are not included in this time period nor the existing requirements are changed. MRP
carries its usual planning outside this fence without interrupting this fenced period.
Configure Planning Time fence and Roll Forward Period
Plant MRP Group Planning Time fence Roll forward Period
0001 0001 14 3-
0001 0002 14 2-
It is logical that any procurement proposal lying outside this fence would start moving in to the fence
one by one; when the fence moves ahead on the time scale. When they move in to this fence, they
are automatically firmed for protection.
Firming for automatically created procurement proposals:
The automatically created procurement proposals in the MRP Run are not firmed by the system, so
that they are available for adjusting dates and quantities in the next planning run, in cases where
there is change in BOM or task list.
You can though manually firm the planned orders individually or collectively using transaction code
MD19
Note - Automatically created planned orders in the planning time fence are only remain firm till they
are in the planning run.
Firming for manually created procurement proposals:
For manually created or changed procurement proposals or even when you reschedule the planned
order in the graphical planning table, the system always marks them with a firming indicator. Though
you can remove or delete this firming indicator.
Firming for component’s planned orders:
In case of a planned order, you can manually firm it by selecting the “firming planned order Indicator”
in the planned order header. And in order to make sure that the BOM levels below are not exploded
or changed in a planning run, you have to set the “firming components indicator”
See the below Example – Planning time fence is 3 days.
Planning
Start
Date
Today –
Day 1
Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8
Planning time fence
Planned
Order 1
Planned
Order 2
Planned
Order 3
Planned Order
4
Planned
Order 5
Planned Order
5
Planned
Order 6
Planned
Order 7
Auto
Firmed
Auto Firmed Auto Firmed Not-firmed Firmed Not-firmed Not-firmed Not-firmed
Next Planning
Start Date
Planning time fence
Planned Order
4
Planned
Order 5
Planned Order
5
Auto Firmed Auto Firmed Auto Firmed
Roll Forward Period
The Roll Forward Period adds the functionality of automatic deletion of firmed planned orders, from
the master plan. It also creates new proposals to cover any requirements pending during the MRP
run. This period can be defined for number of days in past or future. The system deletes all the firmed
planned orders that lie before the roll forward period.
Using the roll forward period, you can have the system delete all useless old firmed planned orders,
which otherwise the system would never had deleted, since they were firmed. This allows for
reorganizing the planned orders.
Configuring SAP MRP Areas
Configuring SAP MRP Areas
Long ago, SAP MRP was only at the plant level or at MRP controller level (activated through a user
exit). Then SAP came up with the concept of running MRP at MRP areas. You can define your own
area for which you want to run MRP without disturbing other areas.
Running MRP for MRP Areas: For running MRP at a MRP area, you would have to create a scope
of planning in MRP configuration, which contain the MRP area or a set of MRP areas arranged in
sequence of planning.
Assigning MRP areas: To have the “MRP Areas” work, you have to activate the MRP areas and
then create them and then assign them to the material master MRP 1 view. If a MRP area is not
assigned to the material, then it will work as per the plant level MRP area.
Configuring MRP areas
Step 1: Activate MRP Area: Use the transaction path: SAP Customizing Implementation Guide >
Production > Material Requirements Planning > Master Data > MRP Areas > Activate MRP for MRP
Areas
Step 2: Define MRP Areas: Use transaction path: SAP Customizing Implementation Guide >
Production > Material Requirements Planning > Master Data > MRP Areas > Define MRP Areas
Types of MRP Areas:
Plant MRP Areas: You can create one MRP area for several plants, so that when you run the MRP
for this MRP area, the run is for all the plants configured in the MRP area.
Storage Location MRP Areas: You can create MRP areas for several storage locations at a plant.
You cannot use one storage location in multiple MRP areas.
Subcontractors MRP Areas: You can create MRP areas for several subcontractors for a plant. You
cannot use one subcontractor in multiple MRP areas.
Configuring SAP MRP Dynamic Safety Stock (Range of coverage Profile)
Configuring SAP MRP Dynamic Safety Stock (Range of coverage Profile)
The Range of coverage profile is configured for the use of Dynamic safety stock for a given material.
The range of coverage configuration contains the parameters for the calculation of the dynamic safety
stock. The dynamic safety stock is a stock calculated based on the average daily requirements for a
period rather than the actual requirements over the period, therefore it is more statistical value rather
than an absolute value.
Safety stock as we know is used to cover the fluctuations in the requirements, so is the dynamic
safety stock, the only difference being, the safety stock is an absolute value provided directly for a
material whereas the dynamic safety stock is calculated by the system on the basis of the coverage
period and average daily stock calculated internally by the system.
The Dynamic safety stock is calculated in every planning run.
The transaction path is: SAP Customizing Implementation Guide > Production > Material
Requirements Planning > Planning > MRP Calculations > Define Range of Coverage Profile
(Dynamic Safety Stock)
Range of coverage Configuration:
Fig MRP - Config 12
Configuration for calculation of average daily requirement for a period
Period indicator - Indicate the type of period, whether week or month or according to PP planning
calendar. (Let’s say it is W – Week)
Number of Periods – Number of periods used to calculate the average daily requirements (Let’s say it
is 13 Weeks)
Type of Period length – It defines the number of days in the period, if the period length is in terms of
workdays, then the factory calendar work days are considered, if the period length is in terms of
calendar days then it is considered in terms of Gregorian calendar, and if it is terms of standard days,
then you would have to enter the number of days in a period in the configuration (Let’s say that the
configuration was done with workdays and the factory calendar has 7 days per week)
Therefore Average daily requirement =
= Requirements in the period (Requirements in 13 Weeks – Lets say 910 Units) / (Number of Periods
– Lets say 13 Weeks) * (Number of days in the period – Lets say 7 days)
= 910 / (13*7)
= 10 Units
Configuration parameters for calculation of Dynamic Safety Stock for the Range of Coverage
You can define 3 different range of coverage – minimum, maximum, and target range of coverage,
which is used to calculate 3 different stocks using the average daily requirements (range of coverage
multiplied by the period length). The Target range of coverage defined here would be used to
calculate the Dynamic Safety Stock for the period of the coverage.
The Period of the coverage is specified in the configuration. The coverage’s and the periods for
which they should work for, are defined for 2 separate period lengths and the 3rd period length is for
the rest of horizon.
In the example, we have defined the safety stock to cover a period of 7 days (minimum, target and
the maximum range of coverage). The minimum, target and the maximum stock is calculated for the
average daily requirement over the respective coverage periods.
You can check the minimum, maximum, target stock levels, minimum range of coverage, maximum
range of coverage, target range of coverage in the MRP List or Stock requirements list’s “Period
Total Display” Section.
As per our example, for the first period of 13 weeks, all the 3 stocks levels – minimum, maximum, and
target stock levels would be 70 Units and for the next period of 26 weeks it will be 70 units as well
and for the rest of the horizon it will be 70 units again.
Normally when the available stock falls below the minimum stock level, SAP planning run, would
immediately create planned orders to suffice at least the target stock level. For example if the
minimum stock level is 30 and the maximum is 80 and the target stock is 50 units, then if the
available stocks fall below the 30 units mark, SAP creates a procurement proposal for 50 units to
reach back to the target stock level. Whereas in the example below, all the 3 stocks types are 70
units, therefore when the stocks fall below the 70 units, the system will try to raise a procurement
proposal to reach back to 70 units.
As per our example in the configuration screen shot –
Dynamic safety stock
formula summarized as =
Average Daily Stock *
Range of coverage
Dynamic safety stocks for
the 1st period of 13 weeks
Dynamic safety stocks for
the 2nd
period of 26 weeks Dynamic safety stocks for
the rest of the Horizon
Minimum safety stock
70 Units 70 Units 70 Units
Target safety stock
70 Units 70 Units 70 Units
Maximum safety stock
70 Units 70 Units 70 Units
Another Example of Dynamic Safety Stock
Fig MRP - Config 14
Step a) Demand for 8 Weeks = 800
Step b) Average Daily Requirements
= 896 Units of Demand for 8 Weeks / (8Weeks * 7 Days Per Week)
= 896/(8*7)
= 896/56
= 16 Units
Step c) Calculation of Safety Stock for the coverage period
As per our example in the configuration screen shot –
For the first period, when the stock falls below 32 units (minimum Stock Level), the SAP MRP run
would create the procurement proposals (Let’s Say planned order) for a quantity to suffice at least the
target safety stock level or the dynamic safety stock level = 8 Units.
Dynamic safety stock
formula summarized as =
Average Daily Stock *
Range of coverage
Dynamic safety stocks for
the 1st period of 8 weeks
Dynamic safety stocks for
the 2nd
period of 8 weeks
Dynamic safety stocks for
the rest of the Horizon
Minimum safety stock
= 2 * 16 = 32 = 2 * 16 = 32 = 2 * 16 = 32
Target safety stock
= 5 * 16 = 80 = 5 * 16 = 80 = 5 * 16 = 80
Maximum safety stock
= 7 * 16 = 112 = 7 * 16 = 112 = 7 * 16 = 112
Configuring SAP MRP Day's Supply and Receipt Day's Supply
Configuring SAP MRP Day's Supply and Receipt Day's Supply
The days of supply is not a mandatory configuration, you can only configure the days supply if you
feel the SAP pre-configured ones are not what you want.
SAP offers 2 types of evaluations in SAP, the days supply and the receipt day’s supply.
In the SAP MRP Evaluation transactions such as stock requirement list or MRP list, the days supply
would calculate the number of days on the time axis, till the material requirements can be satisfied
purely by the current available stock.
While the Receipt Day’s supply would indicate how long would the current stock and the expected
receipts would cover the requirements. There are 2 receipt day’s supply evaluations offered by SAP
called as the receipt day’s supply 1 and receipt days supply 2. SAP offers a configuration to select the
receipts elements for receipt day supply 1 and 2 evaluations. There is also an option to have the
receipt day’s supplies to be calculated when the stocks fall below the safety stock or below the
current available stocks.
The days supply values or the receipt days supply values can be correlated with the range of
coverage concept. These tools comes with traffic lights – red, yellow and green which offer warnings
to the MRP Controllers/users and lets him/her strategically know when the material stock would be
totally consumed out, which would help the planner to foresight and take necessary actions in
advance.
The transaction path for the same is SAP Customizing Implementation Guide > Production > Material
Requirements Planning > Evaluations > Define Receipt Elements for Receipt Days' Supply
Fig MRP - Config 13
Number of Days Stocks will Cover the Requirements
Day’s Supply Receipt Day’s
Supply 1
Receipt Day’s
Supply 2
Consider Current Stocks only in calculation of Days Supply
Only Consider Current available Stocks to cover Requirements
X
Consider Receipts also along with Current Stock in Calculation of Days Supply
Firmed Planned orders,Planned orders assigned with Production versions, Purchase orders, Schedule lines, Firmed
Purchase Requisitions, Receipt Reservations, Shipping Notifications
Consider all the possible receipt elements along with the plant
stock
Example – Firmed Planned orders, Planned orders assigned with
Production versions, Purchase orders, Schedule lines, Firmed
Purchase Requisitions, Receipt Reservations,
X
Consider all the Most Certain receipt elements along with the
plant stock
Example - Production order, Shipping Notifications, QM
Inspection Lots
X
Example for Days Supply and Receipt Days Supply:
Days’ Supply for Material M1 on Today = 3 days
(Receipts are not considered)
Day Requirements Available Qty
Stock Balance Left after covering
Requirements
Today - 20 Current Stock = 100 100 – 20 = 80
2nd
Day - 30 Stock Available = 80 80 – 30 = 50
3rd
Day - 50 Stock Available = 50 50 – 50 = 0 (Stock = 0)
4th
Day - 52
5th
Day - 40
6th
Day - 20
Days’ Supply on Today = Coverage’s Considering without the receipts = 3 Days Exactly
Receipts Days’ Supply for Material M1 on Today = A little more than 4 days
(Receipts are also considered – This example can be for Receipt Days supply 1 or 2)
Day Reqmts Expected Receipts Available Stock
Stock Balance Left after
covering Requirements
Today -
20 Firmed Planned order = 10
Production order = 5
Total Receipts on day = 15
Available = 100 (100 + 15) -20 = 95
2nd
Day -
30 Total Receipts on day = 0 Available = 95
(95 + 0 ) – 30 = 65
3rd
Day -
50 Production order = 25
Total Receipts on day = 25
Available = 65
(65 + 25) – 50 = 40
4th
Day -
47 Planned order = 8
Production order = 5
Total Receipts on day = 13
Available = 40 (40 + 13) – 47 = 6
5th
Day -
40 Planned order = 5
Total Receipts on day = 0
Available = 6 (1 + 5) – 40 = - 34
Shortage
6th
Day -
20
Receipt Day’s Supply on Today = Coverage’s Considering the receipts
= 5 – 1 + (6/40) = 4 + 0.15 = 4.15 Days

More Related Content

What's hot

SAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna NookellaSAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna Nookellamuralikrishnanookella
 
Material master views
Material master viewsMaterial master views
Material master viewsLokesh Modem
 
Sap MRP materials requirements planning
Sap MRP materials requirements planningSap MRP materials requirements planning
Sap MRP materials requirements planningnagarajusap06
 
Make to order document
Make to order document Make to order document
Make to order document Hari Krishna
 
SAP MM Interview questions
SAP MM Interview questionsSAP MM Interview questions
SAP MM Interview questionsIT LearnMore
 
SAP Account determination MM-FI by Odaiah Pelley - 1
SAP Account determination MM-FI by Odaiah Pelley - 1SAP Account determination MM-FI by Odaiah Pelley - 1
SAP Account determination MM-FI by Odaiah Pelley - 1Intelligroup, Inc.
 
SAP Configuration Guide for Functional Modules (Based on IDES)
SAP Configuration Guide for Functional Modules (Based on IDES)SAP Configuration Guide for Functional Modules (Based on IDES)
SAP Configuration Guide for Functional Modules (Based on IDES)sapdocs. info
 
SAP STO config
SAP STO configSAP STO config
SAP STO configsamitchak
 
Mto end to end process demo
Mto end to end process demoMto end to end process demo
Mto end to end process demoGopi Ponnala
 
Functional specification of sap
Functional specification of  sapFunctional specification of  sap
Functional specification of sapSaptechies
 
SAP IS Retail Article Master
SAP IS Retail Article MasterSAP IS Retail Article Master
SAP IS Retail Article Mastersameer311299
 
Pp batch management-presentation
Pp batch management-presentationPp batch management-presentation
Pp batch management-presentationskumar_sap
 
Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...Ankit Sharma
 
Automatic batch determination based on shelf life
Automatic batch determination based on shelf lifeAutomatic batch determination based on shelf life
Automatic batch determination based on shelf lifeMauricio Beltran
 

What's hot (20)

SAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna NookellaSAP PP Case study by Murali Krishna Nookella
SAP PP Case study by Murali Krishna Nookella
 
Transfer of requirements in SAP SD
Transfer of requirements in SAP SDTransfer of requirements in SAP SD
Transfer of requirements in SAP SD
 
SAP MM Standard Business Processes
SAP MM Standard Business ProcessesSAP MM Standard Business Processes
SAP MM Standard Business Processes
 
MRP views in Material Master
MRP views in Material MasterMRP views in Material Master
MRP views in Material Master
 
Material master views
Material master viewsMaterial master views
Material master views
 
Sap MRP materials requirements planning
Sap MRP materials requirements planningSap MRP materials requirements planning
Sap MRP materials requirements planning
 
Availability Check in SAP SD
Availability Check in SAP SDAvailability Check in SAP SD
Availability Check in SAP SD
 
Make to order document
Make to order document Make to order document
Make to order document
 
MRP Live on S/4 HANA
MRP Live on S/4 HANAMRP Live on S/4 HANA
MRP Live on S/4 HANA
 
SAP MM Interview questions
SAP MM Interview questionsSAP MM Interview questions
SAP MM Interview questions
 
SAP Account determination MM-FI by Odaiah Pelley - 1
SAP Account determination MM-FI by Odaiah Pelley - 1SAP Account determination MM-FI by Odaiah Pelley - 1
SAP Account determination MM-FI by Odaiah Pelley - 1
 
SAP Configuration Guide for Functional Modules (Based on IDES)
SAP Configuration Guide for Functional Modules (Based on IDES)SAP Configuration Guide for Functional Modules (Based on IDES)
SAP Configuration Guide for Functional Modules (Based on IDES)
 
SAP STO config
SAP STO configSAP STO config
SAP STO config
 
Mto end to end process demo
Mto end to end process demoMto end to end process demo
Mto end to end process demo
 
Valuation & Split valuation in MM
Valuation & Split valuation in MMValuation & Split valuation in MM
Valuation & Split valuation in MM
 
Functional specification of sap
Functional specification of  sapFunctional specification of  sap
Functional specification of sap
 
SAP IS Retail Article Master
SAP IS Retail Article MasterSAP IS Retail Article Master
SAP IS Retail Article Master
 
Pp batch management-presentation
Pp batch management-presentationPp batch management-presentation
Pp batch management-presentation
 
Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...
 
Automatic batch determination based on shelf life
Automatic batch determination based on shelf lifeAutomatic batch determination based on shelf life
Automatic batch determination based on shelf life
 

Similar to Sap mrp-configuration-pp

17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-infoMBA, MSc, Alberto Castellano
 
SAP MM PP Material requirement planning
SAP MM PP Material requirement planning SAP MM PP Material requirement planning
SAP MM PP Material requirement planning Lokesh Modem
 
Preguntas y respuestas examen de SAP PP
Preguntas y respuestas examen de SAP PPPreguntas y respuestas examen de SAP PP
Preguntas y respuestas examen de SAP PPMario Rodriguez
 
Sap production planning
Sap production planningSap production planning
Sap production planningSourav Dass
 
Sap mrp materials requirements planning
Sap mrp   materials requirements planningSap mrp   materials requirements planning
Sap mrp materials requirements planningmadhu jetty
 
QAD solution (ENG)
QAD solution (ENG)QAD solution (ENG)
QAD solution (ENG)Phu Ton
 
Material Requirements planning system 01Page to 04 Page
Material Requirements planning system                      01Page to 04 PageMaterial Requirements planning system                      01Page to 04 Page
Material Requirements planning system 01Page to 04 PageHasibul Islam
 
Case study industrial equipments & machinery manufacturers
Case study industrial equipments & machinery manufacturersCase study industrial equipments & machinery manufacturers
Case study industrial equipments & machinery manufacturersRoadmapITSolution
 
industrial equipments & machinery manufacturers
industrial equipments & machinery manufacturersindustrial equipments & machinery manufacturers
industrial equipments & machinery manufacturersRoadmapITSolution
 
Roadmap ERP - A Study on ERP Software for Industrial Equipment and Machine Ma...
Roadmap ERP - A Study on ERP Software for Industrial Equipment and Machine Ma...Roadmap ERP - A Study on ERP Software for Industrial Equipment and Machine Ma...
Roadmap ERP - A Study on ERP Software for Industrial Equipment and Machine Ma...Roadmap ERP
 
PP-OVE_1.PPT
PP-OVE_1.PPTPP-OVE_1.PPT
PP-OVE_1.PPTSIPLSIPL
 
SAP ERP1. Describe the Production Planning and Execution process.docx
SAP ERP1. Describe the Production Planning and Execution process.docxSAP ERP1. Describe the Production Planning and Execution process.docx
SAP ERP1. Describe the Production Planning and Execution process.docxkenjordan97598
 
Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)jntuhcej
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGjntuhcej
 

Similar to Sap mrp-configuration-pp (20)

17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
 
SAP MM PP Material requirement planning
SAP MM PP Material requirement planning SAP MM PP Material requirement planning
SAP MM PP Material requirement planning
 
Sap mrp
Sap mrpSap mrp
Sap mrp
 
MRP & ERP.pdf
MRP & ERP.pdfMRP & ERP.pdf
MRP & ERP.pdf
 
Preguntas y respuestas examen de SAP PP
Preguntas y respuestas examen de SAP PPPreguntas y respuestas examen de SAP PP
Preguntas y respuestas examen de SAP PP
 
MRP
MRPMRP
MRP
 
Lect 6.ppt
Lect 6.pptLect 6.ppt
Lect 6.ppt
 
Sap production planning
Sap production planningSap production planning
Sap production planning
 
Mrp 1
Mrp 1Mrp 1
Mrp 1
 
Sap mrp materials requirements planning
Sap mrp   materials requirements planningSap mrp   materials requirements planning
Sap mrp materials requirements planning
 
QAD solution (ENG)
QAD solution (ENG)QAD solution (ENG)
QAD solution (ENG)
 
Material Requirements planning system 01Page to 04 Page
Material Requirements planning system                      01Page to 04 PageMaterial Requirements planning system                      01Page to 04 Page
Material Requirements planning system 01Page to 04 Page
 
Case study industrial equipments & machinery manufacturers
Case study industrial equipments & machinery manufacturersCase study industrial equipments & machinery manufacturers
Case study industrial equipments & machinery manufacturers
 
industrial equipments & machinery manufacturers
industrial equipments & machinery manufacturersindustrial equipments & machinery manufacturers
industrial equipments & machinery manufacturers
 
Roadmap ERP - A Study on ERP Software for Industrial Equipment and Machine Ma...
Roadmap ERP - A Study on ERP Software for Industrial Equipment and Machine Ma...Roadmap ERP - A Study on ERP Software for Industrial Equipment and Machine Ma...
Roadmap ERP - A Study on ERP Software for Industrial Equipment and Machine Ma...
 
PP-OVE_1.PPT
PP-OVE_1.PPTPP-OVE_1.PPT
PP-OVE_1.PPT
 
SAP ERP1. Describe the Production Planning and Execution process.docx
SAP ERP1. Describe the Production Planning and Execution process.docxSAP ERP1. Describe the Production Planning and Execution process.docx
SAP ERP1. Describe the Production Planning and Execution process.docx
 
Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)
 
M-2_CAPP.pptx
M-2_CAPP.pptxM-2_CAPP.pptx
M-2_CAPP.pptx
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
 

More from Lokesh Modem

Variant configuration.docx
Variant configuration.docxVariant configuration.docx
Variant configuration.docxLokesh Modem
 
SAP S4 HANA SOURCING AND PROCUREMENT CONTENT.docx
SAP S4 HANA SOURCING AND PROCUREMENT CONTENT.docxSAP S4 HANA SOURCING AND PROCUREMENT CONTENT.docx
SAP S4 HANA SOURCING AND PROCUREMENT CONTENT.docxLokesh Modem
 
Fiori Apps Library.pdf
Fiori Apps Library.pdfFiori Apps Library.pdf
Fiori Apps Library.pdfLokesh Modem
 
Material Ledger Configuration.doc
Material Ledger Configuration.docMaterial Ledger Configuration.doc
Material Ledger Configuration.docLokesh Modem
 
What is Cost of Goods Sold.doc
What is Cost of Goods Sold.docWhat is Cost of Goods Sold.doc
What is Cost of Goods Sold.docLokesh Modem
 
FSD_Stock aging Report Based On consumption.doc
FSD_Stock aging Report Based On consumption.docFSD_Stock aging Report Based On consumption.doc
FSD_Stock aging Report Based On consumption.docLokesh Modem
 
SAP Solution Manger 7.2
SAP Solution Manger 7.2SAP Solution Manger 7.2
SAP Solution Manger 7.2Lokesh Modem
 
E invoice webinar_jan2020_v2
E invoice webinar_jan2020_v2E invoice webinar_jan2020_v2
E invoice webinar_jan2020_v2Lokesh Modem
 
Gst digital compliance roadmap jan2010 v1
Gst digital compliance roadmap jan2010 v1Gst digital compliance roadmap jan2010 v1
Gst digital compliance roadmap jan2010 v1Lokesh Modem
 
SAP MM Business Scenarios
SAP MM  Business ScenariosSAP MM  Business Scenarios
SAP MM Business ScenariosLokesh Modem
 
SAP Third party scenarios _automatives
SAP Third party scenarios _automatives SAP Third party scenarios _automatives
SAP Third party scenarios _automatives Lokesh Modem
 
Fsd for mass upload program to create and change of scheduling agreement
Fsd for mass upload program to create and change of scheduling agreementFsd for mass upload program to create and change of scheduling agreement
Fsd for mass upload program to create and change of scheduling agreementLokesh Modem
 
Pir price updation in SCHEDULLING AGREEMENT
Pir price updation in SCHEDULLING AGREEMENTPir price updation in SCHEDULLING AGREEMENT
Pir price updation in SCHEDULLING AGREEMENTLokesh Modem
 
Fsd zpriz price details from a017 & a018
Fsd zpriz price details from a017 & a018Fsd zpriz price details from a017 & a018
Fsd zpriz price details from a017 & a018Lokesh Modem
 
Fsd for upload program for delivery completion indicator of scheduling agreem...
Fsd for upload program for delivery completion indicator of scheduling agreem...Fsd for upload program for delivery completion indicator of scheduling agreem...
Fsd for upload program for delivery completion indicator of scheduling agreem...Lokesh Modem
 
Guidelines for xl_filling
Guidelines for xl_fillingGuidelines for xl_filling
Guidelines for xl_fillingLokesh Modem
 
Gst e way bill solution from sap
Gst e way bill solution from sapGst e way bill solution from sap
Gst e way bill solution from sapLokesh Modem
 

More from Lokesh Modem (20)

Variant configuration.docx
Variant configuration.docxVariant configuration.docx
Variant configuration.docx
 
SAP S4 HANA SOURCING AND PROCUREMENT CONTENT.docx
SAP S4 HANA SOURCING AND PROCUREMENT CONTENT.docxSAP S4 HANA SOURCING AND PROCUREMENT CONTENT.docx
SAP S4 HANA SOURCING AND PROCUREMENT CONTENT.docx
 
Fiori Apps Library.pdf
Fiori Apps Library.pdfFiori Apps Library.pdf
Fiori Apps Library.pdf
 
Material Ledger Configuration.doc
Material Ledger Configuration.docMaterial Ledger Configuration.doc
Material Ledger Configuration.doc
 
SAP S4 HANA.docx
SAP S4 HANA.docxSAP S4 HANA.docx
SAP S4 HANA.docx
 
What is Cost of Goods Sold.doc
What is Cost of Goods Sold.docWhat is Cost of Goods Sold.doc
What is Cost of Goods Sold.doc
 
FSD_Stock aging Report Based On consumption.doc
FSD_Stock aging Report Based On consumption.docFSD_Stock aging Report Based On consumption.doc
FSD_Stock aging Report Based On consumption.doc
 
Sap pp org
Sap pp orgSap pp org
Sap pp org
 
Sap sd org
Sap sd org Sap sd org
Sap sd org
 
SAP Solution Manger 7.2
SAP Solution Manger 7.2SAP Solution Manger 7.2
SAP Solution Manger 7.2
 
E invoice webinar_jan2020_v2
E invoice webinar_jan2020_v2E invoice webinar_jan2020_v2
E invoice webinar_jan2020_v2
 
Gst digital compliance roadmap jan2010 v1
Gst digital compliance roadmap jan2010 v1Gst digital compliance roadmap jan2010 v1
Gst digital compliance roadmap jan2010 v1
 
SAP MM Business Scenarios
SAP MM  Business ScenariosSAP MM  Business Scenarios
SAP MM Business Scenarios
 
SAP Third party scenarios _automatives
SAP Third party scenarios _automatives SAP Third party scenarios _automatives
SAP Third party scenarios _automatives
 
Fsd for mass upload program to create and change of scheduling agreement
Fsd for mass upload program to create and change of scheduling agreementFsd for mass upload program to create and change of scheduling agreement
Fsd for mass upload program to create and change of scheduling agreement
 
Pir price updation in SCHEDULLING AGREEMENT
Pir price updation in SCHEDULLING AGREEMENTPir price updation in SCHEDULLING AGREEMENT
Pir price updation in SCHEDULLING AGREEMENT
 
Fsd zpriz price details from a017 & a018
Fsd zpriz price details from a017 & a018Fsd zpriz price details from a017 & a018
Fsd zpriz price details from a017 & a018
 
Fsd for upload program for delivery completion indicator of scheduling agreem...
Fsd for upload program for delivery completion indicator of scheduling agreem...Fsd for upload program for delivery completion indicator of scheduling agreem...
Fsd for upload program for delivery completion indicator of scheduling agreem...
 
Guidelines for xl_filling
Guidelines for xl_fillingGuidelines for xl_filling
Guidelines for xl_filling
 
Gst e way bill solution from sap
Gst e way bill solution from sapGst e way bill solution from sap
Gst e way bill solution from sap
 

Recently uploaded

Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...stazi3110
 
Folding Cheat Sheet #4 - fourth in a series
Folding Cheat Sheet #4 - fourth in a seriesFolding Cheat Sheet #4 - fourth in a series
Folding Cheat Sheet #4 - fourth in a seriesPhilip Schwarz
 
React Server Component in Next.js by Hanief Utama
React Server Component in Next.js by Hanief UtamaReact Server Component in Next.js by Hanief Utama
React Server Component in Next.js by Hanief UtamaHanief Utama
 
Building Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop SlideBuilding Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop SlideChristina Lin
 
chapter--4-software-project-planning.ppt
chapter--4-software-project-planning.pptchapter--4-software-project-planning.ppt
chapter--4-software-project-planning.pptkotipi9215
 
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024StefanoLambiase
 
Unveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML DiagramsUnveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML DiagramsAhmed Mohamed
 
Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)OPEN KNOWLEDGE GmbH
 
MYjobs Presentation Django-based project
MYjobs Presentation Django-based projectMYjobs Presentation Django-based project
MYjobs Presentation Django-based projectAnoyGreter
 
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...MyIntelliSource, Inc.
 
Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...OnePlan Solutions
 
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdfGOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdfAlina Yurenko
 
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptxKnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptxTier1 app
 
software engineering Chapter 5 System modeling.pptx
software engineering Chapter 5 System modeling.pptxsoftware engineering Chapter 5 System modeling.pptx
software engineering Chapter 5 System modeling.pptxnada99848
 
Salesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantSalesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantAxelRicardoTrocheRiq
 
Asset Management Software - Infographic
Asset Management Software - InfographicAsset Management Software - Infographic
Asset Management Software - InfographicHr365.us smith
 
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...Christina Lin
 
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...MyIntelliSource, Inc.
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software DevelopersVinodh Ram
 
Cloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEECloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEEVICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
 
Folding Cheat Sheet #4 - fourth in a series
Folding Cheat Sheet #4 - fourth in a seriesFolding Cheat Sheet #4 - fourth in a series
Folding Cheat Sheet #4 - fourth in a series
 
React Server Component in Next.js by Hanief Utama
React Server Component in Next.js by Hanief UtamaReact Server Component in Next.js by Hanief Utama
React Server Component in Next.js by Hanief Utama
 
Building Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop SlideBuilding Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
 
chapter--4-software-project-planning.ppt
chapter--4-software-project-planning.pptchapter--4-software-project-planning.ppt
chapter--4-software-project-planning.ppt
 
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
 
Unveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML DiagramsUnveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML Diagrams
 
Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)
 
MYjobs Presentation Django-based project
MYjobs Presentation Django-based projectMYjobs Presentation Django-based project
MYjobs Presentation Django-based project
 
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
 
Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...
 
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdfGOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
 
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptxKnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
KnowAPIs-UnknownPerf-jaxMainz-2024 (1).pptx
 
software engineering Chapter 5 System modeling.pptx
software engineering Chapter 5 System modeling.pptxsoftware engineering Chapter 5 System modeling.pptx
software engineering Chapter 5 System modeling.pptx
 
Salesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantSalesforce Certified Field Service Consultant
Salesforce Certified Field Service Consultant
 
Asset Management Software - Infographic
Asset Management Software - InfographicAsset Management Software - Infographic
Asset Management Software - Infographic
 
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
 
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software Developers
 
Cloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEECloud Data Center Network Construction - IEEE
Cloud Data Center Network Construction - IEEE
 

Sap mrp-configuration-pp

  • 1. SAP MRP Configuration Activating MRP and Planning File Entry a) Activating SAP's Material Requirements Planning (MRP) This configuration allows you to choose the plant for which you would want to activate SAP Material Requirement Planning (SAP MRP). Activating MRP for the plant allows one to use the SAP MRP tool for the plant. SAP Transaction code OMDU and the SAP path is Logistics > Production > MRP > Planning File Entry > Activate MRP and Set up Planning File b) Activating Planning File Entries for a Plant Activating Planning file entry for the plant (through a variant that can be rescheduled) allows you to collect all the material in a planning file list, which has an MRP Type in the material master MRP 1 View (other than MRP Type XO) The process of recording a planning file entry for a material, can be run periodically using a batch job scheduling method. The transaction code to set up the variant and period scheduling is OMDO and the Path for activating the planning file set up is Logistics > Production > MRP > Planning File Entry > Activate MRP and Set up Planning File All the entries in the planning file will have a “change indicator” specifying that a material has undergone a change (change in receipts elements or issues elements). This indicator will help you to choose only those materials that have undergone a change, through the use of planning key called “Net Change Planning” when running MRP. The planning file record for a material also has a “net change planning in the current horizon” field which will be set if the change in the materials receipt or issue element is valid in the planning horizon. This indicator will help you choose only those materials which have undergone a change in the planning horizon; through the use of a planning key, in an MRP run, called “Net change planning in the planning horizon”. Plant Level configuration for MRP Plant Level configuration for MRP SAP MRP is run at plant level or at a group of plant level (called as scope of planning), thus the MRP configuration is done at Plant level. The configuration done for SAP MRP at Plant level would also be true for SAP Consumption Based Planning (SAP CBP) settings. Transaction code OPPQ takes you in to the SAP MRP configuration called as – Plant Parameters for Material Requirement Planning. The Path which can be used is Logistics > Production > Material Requirement Planning > Plant Parameters > Carry out Overall Maintenance of Plant Parameters.
  • 2. The Transaction code for Consumption Based planning is OMI8 and the Path is Logistics > Materials Management > Consumption Based Planning > Plant Parameters > Carry out Overall Maintenance of Plant Parameters. Fig MRP - Config 1 In the transaction code for Plant level parameters for SAP MRP, you should first input the plant and press the maintain button. If you have already maintained the configuration for the parameters, then it states so, if you haven’t then it simply says – “To Maintain” next to the parameter
  • 3. Fig MRP - Config 2 Following are the parameters that need to maintain as a part of SAP MRP/CBP Configuration: a) Number ranges The number range ID’s are maintained for the following objects: the Planned orders the reservations, the dependent requirements, the simulative dependent requirements, the purchase requisitions, the MRP Lists, In this section only the number range ID’s are maintained. While the actual number range is configured, for the number range ID, using a transaction code OMI2 (for the above mentioned objects created in the planning run). One can also use the transaction code OMI3 for the objects created manually in the front end. Every number range interval, created using OMI2 and OM13, has an ID, which can be allocated to the objects at plant level, i.e., every plant can have a different number range for the objects mentioned above.
  • 4. b) Availability Check rule for Backorder Processing As per standard SAP, the Availability checking rule for the backorder processing is “PP”, though you can have your own availability check rules created or configured. Every Availability checks rule (availability checking scope defined) has a set of receipts (Purchase orders, Production orders) and issues (Sales orders, dependent requirements, reservations, planned independent requirements etc) which are to be considered or not to be considered during the SAP availability checks. To have the checking rule work along with the configuration, you should have the Availability checking groups maintained in the material master. The Checking groups are configured to be associated with the checking rules (checking scopes). The availability checking rule (checking rule scope) has to be maintained, for a given SAP functionality and it has to be assigned to the availability checking group maintained in the material master. The SAP functionalities that use availability checks to check the availability of the header materials as well as components at the plant at the time of sales order creation, the availability checks of the header material at the time of sales order delivery, the availability checks for components in production – thus reporting the missing parts list, the backorder processing etc. c) Reporting This configuration is used for the following purposes. • To configure the objects, which are to be considered in the calculation of the “receipts days supply” like the production orders/process orders, firmed planned orders, purchase orders, assigned planned orders, firmed purchase requisitions, QM Inspection lots, reservations, safety stocks • To configure the reporting of “periods totals” in terms of a defined period (day, week, month, periods as per planning calendar) of in Stock requirement list, MRP list, simulative MPR or interactive MRP d) MRP Controllers This is a mandatory configuration. Here you can configure the list of MRP controllers for the plant. A MRP Controller is a person or a group of people, which is responsible for planning a material or a given list of materials. You have to assign the MRP controller to the Material Master MRP 1 View, so as to delegate the responsibility of the planning and evaluation of planning for that material.
  • 5. e) Floats Floats are buffers in the total lead time, that are provided in production/process order or in the planned orders created manually or during an MRP run. The schedule margin key is used in the Material Master MRP 2 View. It is used in MRP as well as in production order. The floats are defined using the scheduling margin key. Opening period: Number of working days between the date that the order is created and the planned start date. This time is available for the MRP controller to convert a planned order into a purchase requisition or a production order. Float after production: Number of working days between the scheduled finish date and the order finish date; used as a float in production scheduling. Float before production: Number of working days between the order start date and the scheduled start date; used as a float in production. Scheduling release period: Number of workdays between the planned start date and the date for releasing the order. If the order release indicator is set, the production order is released by a background program that takes all dates into account. Plant Plant Name Margin Key Opening Period (In Days) Fl. Before Production (In Days) Fl. After Production (In Days) Release Period (In Days) 0001 0001 001 5 2 2 5 0001 0001 002 5 3 3 5 0001 0001 002 5 4 4 5 f) Special Procurement The special procurement function helps you to configure and assign special procurement to the materials which can be used during an MRP run while creating the procurement proposal. The special procurement functions are withdrawal from alternate plant, production in alternate plant, subcontracting, direct production, phantom item planning, https://sites.google.com/site/sapswords/home/learn-sap-pp/sap-material-master/sap-mrp2-view Example: For Stock Transfer from Plant C001 to Plant C002
  • 6. Create the Special procurement key (Key number = 12 as an example) in the plant C002 with the procurement type as “F” and special procurement as “U” (Stock transfer) and the special procurement plant as “C001”. Normally when creating the special procurement key use Z, Y or X to the Key number, so instead of having Key number as 12, we could have something like Z2 or YA etc. Fig MRP - Config 3 Similarly for Withdrawal from Alternate plant, you could have a Configuration as below: Fig MRP - Config 4 Similarly for Subcontracting, you could have a Configuration as below:
  • 7. Fig MRP - Config 5 Similarly for Production in alternate plant, you could have a Configuration as below: Fig MRP - Config 6 g) Conversion for Planned orders In this configuration parameter, you can maintain the production order type or the process order type, which the system should use as default during the planned order conversion. Setting defaults in the plant parameters configuration allows the system to fix and select the order type for a plant during the conversion process. Note: This can be a useful tool when you are using one production order type and one process order type, but if you are using multiple production/process order types, then you should not be maintaining defaults here.
  • 8. Also for the purchase requisition conversion, you are given an option in the configuration to define the maximum number of planned orders that can be converted in to Purchase requisition. Fig MRP - Config 7 g) Dependent Requirements availability check When carrying out the availability check for each of the components in a MRP BOM explosion, the system needs to know the availability checking scope rule. Again we would maintain the standard Checking rule as PP or you could alternatively configure one for yourselves. h) BOM/Routing Selection ID This configuration parameter is really important and it is mandatory to maintain one, since it helps selection of BOM and task lists in the planned orders. Though there is one more place in the planned order Scheduling parameters MRP configuration, where you can maintain the selection ID for selection of the Task lists (Routing/Recipe/Rate Routing). A selection procedure is set to select BOM or Routing/Recipe on priorities set for the BOM usage or for the task list types and the task list status. Knowing the selection procedures allows the MRP run to select the right BOM and task list for the planned orders. In other words, you could have the BOM Selection being set for selection of the Production BOM Usage first and if a BOM for the material with the Usage – production (Usage = 1), is not found, you could have the system search for a BOM of universal Usage (Usage = 3). Similarly, you could have a task list of type Routing or Recipe or reference operation sets selected and set in priorities of selection (1st – Routing, 2nd – Reference operation sets, 3rd, which has a Status Released for all purposes or released for costing) etc. h) Scheduling of Planned orders
  • 9. This configuration parameter is really important and it is mandatory to maintain one. It allows you to set the control parameters for scheduling of planned orders of type LA at a given plant and for a given MRP Controller. You can leave the MRP controller as “*” to have the scheduling parameters true for all the planned orders across all the MRP controllers. The following control parameters can be configured here:  The Routing/Recipe Selection ID, specifying the routing/recipe that would be selected for detailed scheduling, as per the priorities set for task list type and task list status.  The Detailed scheduling, using the task list is only carried for the scheduling Horizon mentioned, i.e., if the planned orders dates lie beyond the scheduling horizon, then the basic date scheduling is used where the in house production times from the material master is used.  Allow Scheduling Indicator allows the planned orders to be scheduled using the detailed scheduling or basic date scheduling, either of the two, depending upon the availability of the task list and scheduling type selected for the MRP run.  Generate Capacity requirements indicator allows generation of the capacity requirements for the work centers and loads them accordingly. The loading of the work centers is as per the use of the work center determined through the scheduling carried out.  The Task list selection, scheduling horizon, scheduling indicator and the capacity indicator can also be set for rough cut planning used for Long term planning purposes.  The next configuration parameter talks about the configuration of the selection of the type of scheduling level that should be used for adjusting the basic dates of planned orders. The various options available are rate based scheduling, lead time scheduling, scheduling using takt times.  The Adjust planned order dates configuration option allows you to readjust the scheduling results or the basic dates every time you carry out Scheduling. Though there is one more scheduling configuration option provided by the system for overwriting/adjusting the existing basic dates by the new dates arrived at, through rescheduling (using the scheduling level as mentioned). The system not only offers an option to adjust the basic dates for the planned order arrived at by using the scheduling level set, but it also setting the dates of the dependent requirements to the operation start date or the order start date. This configuration not only adjusts or sets the dates of the header planned order and the dependent planned orders, but it also generates capacity requirements for the same. See below for the details of adjusting dates in scheduling and adjusting dates for capacity requirement generation:  You can adjust the Basic Dates of the header planned order using the scheduling level and adjust (or set) the dependent requirements to the start of the header planned order
  • 10.  You can adjust the Basic Dates of the header planned order using the scheduling level and adjust (or set) the dependent requirements to the start of the respective operation to which the dependent requirements are assigned to  You can decide not to adjust the Basic Dates of the header planned order arrived at by using the scheduling level and at the same time not-adjust (or not set) the dependent requirements to the start of the header planned order  You can decide not to adjust the Basic Dates of the header planned order arrived at by using the scheduling level and at the same time not-adjust (not set) the dependent requirements to the start of the respective operations to which the dependent requirements are assigned to  You are also provided an option to configure the scheduling type – whether forward or backward scheduling. It is a normal behavior for the standard system to have this configured as “backward scheduling” so that SAP MRP (material requirement planning) never misses the customer delivery date or order availability date. An option is also provided to not-to-schedule, any orders during the breaks set in the factory calendar.  Start date in the in the past options allows you to push the start date of the planned orders to a certain number of days in past. If the order start date goes beyond the number of days allowed, then the system uses the concept of ‘today’s scheduling” and sets the start date of the planned order to today’s date and carrying out forward scheduling there-after.  One of the scheduling parameters is “reduction measures”, used to reduce the total order lead time in circumstances designed. You can avoid configuration of reduction measures, if you are not using it.
  • 11. Fig MRP - Config 8 i) Default Values for External Processing For external purchasing, one can maintain the default lead time required for conversion of Purchase requisition into purchase order, using the planned delivery lead times from the purchase info record or purchasing agreement. So as to use the planned delivery times from the purchase info record, one should also maintain the source list for the material, with the same vendor in the source list and the purchase info record. Using the planned delivery times from the material master or from purchase info record, is totally a decision of the consultant. It is indeed a nice additional option provided by SAP for using the lead time from info records. j) Planning Horizon Maintaining a planning horizon helps the system to plan only those demands, which fall in the planning horizon starting from today. When an MRP Run is taken, the planning horizon is number of work days as mentioned (let’s say 180 days) from today’s date; the system would not plan any orders whose start date lies beyond this horizon.
  • 12. k) Available stock for net requirement calculations SAP MRP offers you a choice to select the most controversial stock types, in its net requirement calculations. The stock types are – stock in transfer (stock in transfer is considered as stock at the receiving plant as it is already issued from the sending plant), blocked stock, restricted batch stock (stock of batches marked with restricted batch) Fig MRP - Config 9 l) Option to trigger direct Production in MRP or in production planning j) Allowing start date in the past MRP Group Level configuration for MRP MRP Group Level configuration for MRP The entire configuration that is created as a part of SAP MRP Plant level parameter in the above steps can be also set for an MRP Group. You can group materials using MRP Groups. Each of the MRP Group can have its own MRP Parameter set. You can set the MRP group in the material master MRP 1 View. MRP Group can be maintained using transaction code OPPR or the transaction path – Logistics > Production > MRP > MRP Groups > Advantage of working with MRP Groups:
  • 13. Working with MRP groups can be convenient for a plant or an organization, since by assigning the MRP groups to a set of materials, would allow planner to configure these materials (through MRP Groups) to behave in a certain manner for planning purposes. In other words, all the materials in the group would then have a unique planning method or unique planning features. Thus the organization can device multiple MRP groups with their own planning features and characteristics rather than having one set of planning features set at the plant level. The group could have its own unique: Strategy group, Conversion order types, Planning horizon, Planning time fence and roll forward periods, BOM and task list selection ID’s, Direct procurement parameters, Planned order scheduling parameters, Start number of days allowed in the past Availability checking groups, Strategy Groups The strategy groups can be set for a given MRP group at a given plant. The strategy group consists of a number of planning strategies assigned in a sequence of priorities. In other words, the strategy groups, groups together the relevant planning strategies of a material. If you don’t see the default strategy groups, then we would have to manually maintain the strategy groups on the materials MRP 3 view. Defaulting the strategy groups is a nice idea when the strategy groups would remain the same across all the materials which would be assigned with a given strategy group. For example: A material can have the priority 1 strategy as Made-to-Stock (planning strategy 40) and then priority 2 planning strategy as Made-to-Order (planning strategy 20). Assigning this “strategy group” for a MRP group in the MRP Group Parameters configuration and then subsequently assigning the MRP Group to the material master would make the material work on a planning strategy 40 and planning strategy 20 in a sequence of priority. The primary strategy for the material is 40 – Made-to-stock while the secondary strategy is 20 – Made-to-order, which means that every time you plan or produce a material or create a sales order for the material it will always primarily work as a made-to-stock material. Nevertheless, you can also make to material work as a made-to-order material, by changing the requirement type – “KE” of the material in the sales order procurement tab, to suit for made-to-order, which the system would allow since the material’s secondary planning strategy is made-to-order. Configuring SAP MRP Types Configuration of SAP MRP Types
  • 14. In all probabilities, MRP Types is not something which one should configure in SAP; it is used as a standard configuration. Nevertheless, a consultant should know the importance of MRP types and the involved pre-configured parameters. Fig MRP - Config 10 a) MRP Procedures MRP Procedures defines the type of MRP to be used – Reorder point planning methods, Material requirement planning or demand based planning methods, Forecast based planning methods, Time phased planning methods, MPS and the no planning procedures to mark a material with a MRP types that does not plan a material at all. b) Firming Type In the category of MRP procedure called – MRP or demand based planning method and MPS, SAP offers 8 different MRP types with Firming namely P1, P2, P3, P4 and M0, M1, M2, M3, M4. When working with the planning time fence, one needs to set the firming methods & the scheduling methods of the procurement proposals within the planning time fence. 0 1 2 3 4
  • 15. Firming type MRP Types M0 P1 M1 P2 M2 P3 M3 P4 M4 Firming Methods for Procurement Proposals in the Planning time fence No Firming of Procurement Proposals within the planning time fence X Automatic Firming of Procurement Proposals within the planning time fence X X Manual Firming of Procurement within the planning time fence (No Automatic Firming of the procurement proposals ) X X Treatment with New Order Proposals in the Planning time Fence Automatic Creation of New Procurement Proposals to cover the shortages within the planning time fence. But the dates of these new Procurement Proposals are pushed outside the planning time fence X X No New Procurement Proposals created to Cover the material shortages within the planning time fence X X c) Include External Requirements The inclusion of external requirements in net requirement calculations is available to be set, when you are working with reorder point planning based MRP types. Actually there are 2 options in this field, i.e., include external requirements in the total planning horizon or restrict the inclusion of the external requirements only within the replenishment lead time. For example: If the external requirements are set to be considered in the total horizon (of 7 weeks) then in the today’s MRP run, the Customer demand will be considered as it falls in the planning horizon and it will reduce the warehouse stock proportionately which would trigger the reorder point planning procurement once the stock falls below the reorder point. If the external requirements are set to be considered in the Replenishment lead time, let’s say the Replenishment lead time is 1 week, then in that case, only in a MRP run triggered one week before the start date of the external demand, this customer demand will be considered, thus triggering reduction in warehouse stocks.
  • 16. Fig MRP - Config 11 SAP also offers an option to select the additional external requirements that should also be included in the net requirement planning calculations like the - components supplied to the vendor in a subcontracting case, reservations set for the components in a production order, reservations of components in plant maintenance orders, requirements to satisfy the Stock transfer order to another plant, stock transfer requisitions created for Stock transfer orders, requirements raised because of stock transfer delivery schedules. c) Forecasting for MRP Forecasting MRP Types have a “forecasting indicator” as obligatory, unlike other MRP types which normally have the forecasting indicator set to optional. Also the historical data is updated in the material master as total consumption (planned consumption plus unplanned consumption) or unplanned consumption. When the consumption is planned as per the MRP reservations, planned consumption is updated and when the consumption is not planned as per the reservation or is greater than the reservation quantities, then unplanned consumption is updated. In MRP type configuration, you have an option of choosing the type of historical consumption of a material to be used for planning whether total consumption (planned + unplanned consumption) or unplanned consumption. After choosing the historical date type, you should configure, the type of forecast requirements to be considered in MRP planning run, whether total consumption (planned + unplanned consumption) or unplanned consumption. The reduction method for forecast requirements is also configurable. The default is reduction by consumption. d) Planning method
  • 17. The MRP type offers you to plan the materials in an external system, like the MRP Type X0. The indicator called the planning method allows you to choose external planning so as to plan materials in the external system. e) Automatic Calculations You can have the safety stock and the reorder point calculated automatically by the system, when you are using the automatic reorder point planning methods. In the automatic calculations the system uses the forecast data. Configuring SAP MRP Scope of Planning for the Total Planning Run Configuring SAP MRP Scope of Planning for the Total Planning Run SAP provides an option to plan multiple plants together or multiple MRP areas in one planning run in a sequence. Transaction code OM0E can be used for configuration or the logical SAP path – SAP Customizing Implementation Guide > Production > MRP > Planning > Define Scope of Planning for Total Planning, can be used to configure. Step 1 – Define the Name of the Scope of planning run Step 2 – Define the plants or MRP areas to be included in the planning run arranged in a sequence. The sequence is defined by the first field called Configuring SAP MRP Planning time fence and Roll Forward Period Configuring SAP MRP Planning time fence and Roll Forward Period The transaction path to configure the planning time fence and roll forward period is: SAP Customizing Implementation Guide > Production > Material Requirements Planning > Planning > MRP Areas > MRP Calculation > Define Planning Time Fence and Roll Forward Period Planning Time Fence: The planning time fence is the number of work days, within which you can protect the master plan (or in other words the procurement proposals of a master plan) from being disturbed or changed from any automatic changes (of an MRP Run). The procurement proposals are firmed so as to protect them from any changes. The firming of the procurement proposals (planned orders, purchase requisitions, delivery schedules) in the planning time fence prevents the proposals in the time fence from being adopted in the next planning run.
  • 18. In other words, in the planning time fence, the system does not create or delete any procurement proposals nor does it changes the existing proposals. The system calculates the time fence from today’s date plus the “number of days mentioned as planning time fence” in the material master or in the MRP configuration (where you can define the planning time fence for plant or for a given MRP group). It is needless to say that any new requirements are not included in this time period nor the existing requirements are changed. MRP carries its usual planning outside this fence without interrupting this fenced period. Configure Planning Time fence and Roll Forward Period Plant MRP Group Planning Time fence Roll forward Period 0001 0001 14 3- 0001 0002 14 2- It is logical that any procurement proposal lying outside this fence would start moving in to the fence one by one; when the fence moves ahead on the time scale. When they move in to this fence, they are automatically firmed for protection. Firming for automatically created procurement proposals: The automatically created procurement proposals in the MRP Run are not firmed by the system, so that they are available for adjusting dates and quantities in the next planning run, in cases where there is change in BOM or task list. You can though manually firm the planned orders individually or collectively using transaction code MD19 Note - Automatically created planned orders in the planning time fence are only remain firm till they are in the planning run. Firming for manually created procurement proposals: For manually created or changed procurement proposals or even when you reschedule the planned order in the graphical planning table, the system always marks them with a firming indicator. Though you can remove or delete this firming indicator. Firming for component’s planned orders: In case of a planned order, you can manually firm it by selecting the “firming planned order Indicator” in the planned order header. And in order to make sure that the BOM levels below are not exploded or changed in a planning run, you have to set the “firming components indicator”
  • 19. See the below Example – Planning time fence is 3 days. Planning Start Date Today – Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Planning time fence Planned Order 1 Planned Order 2 Planned Order 3 Planned Order 4 Planned Order 5 Planned Order 5 Planned Order 6 Planned Order 7 Auto Firmed Auto Firmed Auto Firmed Not-firmed Firmed Not-firmed Not-firmed Not-firmed Next Planning Start Date Planning time fence Planned Order 4 Planned Order 5 Planned Order 5 Auto Firmed Auto Firmed Auto Firmed Roll Forward Period The Roll Forward Period adds the functionality of automatic deletion of firmed planned orders, from the master plan. It also creates new proposals to cover any requirements pending during the MRP run. This period can be defined for number of days in past or future. The system deletes all the firmed planned orders that lie before the roll forward period. Using the roll forward period, you can have the system delete all useless old firmed planned orders, which otherwise the system would never had deleted, since they were firmed. This allows for reorganizing the planned orders. Configuring SAP MRP Areas Configuring SAP MRP Areas Long ago, SAP MRP was only at the plant level or at MRP controller level (activated through a user exit). Then SAP came up with the concept of running MRP at MRP areas. You can define your own area for which you want to run MRP without disturbing other areas. Running MRP for MRP Areas: For running MRP at a MRP area, you would have to create a scope of planning in MRP configuration, which contain the MRP area or a set of MRP areas arranged in sequence of planning.
  • 20. Assigning MRP areas: To have the “MRP Areas” work, you have to activate the MRP areas and then create them and then assign them to the material master MRP 1 view. If a MRP area is not assigned to the material, then it will work as per the plant level MRP area. Configuring MRP areas Step 1: Activate MRP Area: Use the transaction path: SAP Customizing Implementation Guide > Production > Material Requirements Planning > Master Data > MRP Areas > Activate MRP for MRP Areas Step 2: Define MRP Areas: Use transaction path: SAP Customizing Implementation Guide > Production > Material Requirements Planning > Master Data > MRP Areas > Define MRP Areas Types of MRP Areas: Plant MRP Areas: You can create one MRP area for several plants, so that when you run the MRP for this MRP area, the run is for all the plants configured in the MRP area. Storage Location MRP Areas: You can create MRP areas for several storage locations at a plant. You cannot use one storage location in multiple MRP areas. Subcontractors MRP Areas: You can create MRP areas for several subcontractors for a plant. You cannot use one subcontractor in multiple MRP areas. Configuring SAP MRP Dynamic Safety Stock (Range of coverage Profile) Configuring SAP MRP Dynamic Safety Stock (Range of coverage Profile) The Range of coverage profile is configured for the use of Dynamic safety stock for a given material. The range of coverage configuration contains the parameters for the calculation of the dynamic safety stock. The dynamic safety stock is a stock calculated based on the average daily requirements for a period rather than the actual requirements over the period, therefore it is more statistical value rather than an absolute value. Safety stock as we know is used to cover the fluctuations in the requirements, so is the dynamic safety stock, the only difference being, the safety stock is an absolute value provided directly for a material whereas the dynamic safety stock is calculated by the system on the basis of the coverage period and average daily stock calculated internally by the system. The Dynamic safety stock is calculated in every planning run.
  • 21. The transaction path is: SAP Customizing Implementation Guide > Production > Material Requirements Planning > Planning > MRP Calculations > Define Range of Coverage Profile (Dynamic Safety Stock) Range of coverage Configuration: Fig MRP - Config 12 Configuration for calculation of average daily requirement for a period Period indicator - Indicate the type of period, whether week or month or according to PP planning calendar. (Let’s say it is W – Week) Number of Periods – Number of periods used to calculate the average daily requirements (Let’s say it is 13 Weeks) Type of Period length – It defines the number of days in the period, if the period length is in terms of workdays, then the factory calendar work days are considered, if the period length is in terms of calendar days then it is considered in terms of Gregorian calendar, and if it is terms of standard days, then you would have to enter the number of days in a period in the configuration (Let’s say that the configuration was done with workdays and the factory calendar has 7 days per week) Therefore Average daily requirement = = Requirements in the period (Requirements in 13 Weeks – Lets say 910 Units) / (Number of Periods – Lets say 13 Weeks) * (Number of days in the period – Lets say 7 days) = 910 / (13*7)
  • 22. = 10 Units Configuration parameters for calculation of Dynamic Safety Stock for the Range of Coverage You can define 3 different range of coverage – minimum, maximum, and target range of coverage, which is used to calculate 3 different stocks using the average daily requirements (range of coverage multiplied by the period length). The Target range of coverage defined here would be used to calculate the Dynamic Safety Stock for the period of the coverage. The Period of the coverage is specified in the configuration. The coverage’s and the periods for which they should work for, are defined for 2 separate period lengths and the 3rd period length is for the rest of horizon. In the example, we have defined the safety stock to cover a period of 7 days (minimum, target and the maximum range of coverage). The minimum, target and the maximum stock is calculated for the average daily requirement over the respective coverage periods. You can check the minimum, maximum, target stock levels, minimum range of coverage, maximum range of coverage, target range of coverage in the MRP List or Stock requirements list’s “Period Total Display” Section. As per our example, for the first period of 13 weeks, all the 3 stocks levels – minimum, maximum, and target stock levels would be 70 Units and for the next period of 26 weeks it will be 70 units as well and for the rest of the horizon it will be 70 units again. Normally when the available stock falls below the minimum stock level, SAP planning run, would immediately create planned orders to suffice at least the target stock level. For example if the minimum stock level is 30 and the maximum is 80 and the target stock is 50 units, then if the available stocks fall below the 30 units mark, SAP creates a procurement proposal for 50 units to reach back to the target stock level. Whereas in the example below, all the 3 stocks types are 70 units, therefore when the stocks fall below the 70 units, the system will try to raise a procurement proposal to reach back to 70 units. As per our example in the configuration screen shot – Dynamic safety stock formula summarized as = Average Daily Stock * Range of coverage Dynamic safety stocks for the 1st period of 13 weeks Dynamic safety stocks for the 2nd period of 26 weeks Dynamic safety stocks for the rest of the Horizon Minimum safety stock 70 Units 70 Units 70 Units Target safety stock 70 Units 70 Units 70 Units
  • 23. Maximum safety stock 70 Units 70 Units 70 Units Another Example of Dynamic Safety Stock Fig MRP - Config 14 Step a) Demand for 8 Weeks = 800 Step b) Average Daily Requirements = 896 Units of Demand for 8 Weeks / (8Weeks * 7 Days Per Week) = 896/(8*7) = 896/56 = 16 Units Step c) Calculation of Safety Stock for the coverage period As per our example in the configuration screen shot – For the first period, when the stock falls below 32 units (minimum Stock Level), the SAP MRP run would create the procurement proposals (Let’s Say planned order) for a quantity to suffice at least the target safety stock level or the dynamic safety stock level = 8 Units. Dynamic safety stock formula summarized as = Average Daily Stock * Range of coverage Dynamic safety stocks for the 1st period of 8 weeks Dynamic safety stocks for the 2nd period of 8 weeks Dynamic safety stocks for the rest of the Horizon
  • 24. Minimum safety stock = 2 * 16 = 32 = 2 * 16 = 32 = 2 * 16 = 32 Target safety stock = 5 * 16 = 80 = 5 * 16 = 80 = 5 * 16 = 80 Maximum safety stock = 7 * 16 = 112 = 7 * 16 = 112 = 7 * 16 = 112 Configuring SAP MRP Day's Supply and Receipt Day's Supply Configuring SAP MRP Day's Supply and Receipt Day's Supply The days of supply is not a mandatory configuration, you can only configure the days supply if you feel the SAP pre-configured ones are not what you want. SAP offers 2 types of evaluations in SAP, the days supply and the receipt day’s supply. In the SAP MRP Evaluation transactions such as stock requirement list or MRP list, the days supply would calculate the number of days on the time axis, till the material requirements can be satisfied purely by the current available stock. While the Receipt Day’s supply would indicate how long would the current stock and the expected receipts would cover the requirements. There are 2 receipt day’s supply evaluations offered by SAP called as the receipt day’s supply 1 and receipt days supply 2. SAP offers a configuration to select the receipts elements for receipt day supply 1 and 2 evaluations. There is also an option to have the receipt day’s supplies to be calculated when the stocks fall below the safety stock or below the current available stocks. The days supply values or the receipt days supply values can be correlated with the range of coverage concept. These tools comes with traffic lights – red, yellow and green which offer warnings to the MRP Controllers/users and lets him/her strategically know when the material stock would be totally consumed out, which would help the planner to foresight and take necessary actions in advance. The transaction path for the same is SAP Customizing Implementation Guide > Production > Material Requirements Planning > Evaluations > Define Receipt Elements for Receipt Days' Supply
  • 25. Fig MRP - Config 13 Number of Days Stocks will Cover the Requirements Day’s Supply Receipt Day’s Supply 1 Receipt Day’s Supply 2 Consider Current Stocks only in calculation of Days Supply Only Consider Current available Stocks to cover Requirements X Consider Receipts also along with Current Stock in Calculation of Days Supply Firmed Planned orders,Planned orders assigned with Production versions, Purchase orders, Schedule lines, Firmed Purchase Requisitions, Receipt Reservations, Shipping Notifications Consider all the possible receipt elements along with the plant stock Example – Firmed Planned orders, Planned orders assigned with Production versions, Purchase orders, Schedule lines, Firmed Purchase Requisitions, Receipt Reservations, X Consider all the Most Certain receipt elements along with the plant stock Example - Production order, Shipping Notifications, QM Inspection Lots X Example for Days Supply and Receipt Days Supply:
  • 26. Days’ Supply for Material M1 on Today = 3 days (Receipts are not considered) Day Requirements Available Qty Stock Balance Left after covering Requirements Today - 20 Current Stock = 100 100 – 20 = 80 2nd Day - 30 Stock Available = 80 80 – 30 = 50 3rd Day - 50 Stock Available = 50 50 – 50 = 0 (Stock = 0) 4th Day - 52 5th Day - 40 6th Day - 20 Days’ Supply on Today = Coverage’s Considering without the receipts = 3 Days Exactly Receipts Days’ Supply for Material M1 on Today = A little more than 4 days (Receipts are also considered – This example can be for Receipt Days supply 1 or 2) Day Reqmts Expected Receipts Available Stock Stock Balance Left after covering Requirements Today - 20 Firmed Planned order = 10 Production order = 5 Total Receipts on day = 15 Available = 100 (100 + 15) -20 = 95 2nd Day - 30 Total Receipts on day = 0 Available = 95 (95 + 0 ) – 30 = 65 3rd Day - 50 Production order = 25 Total Receipts on day = 25 Available = 65 (65 + 25) – 50 = 40 4th Day - 47 Planned order = 8 Production order = 5 Total Receipts on day = 13 Available = 40 (40 + 13) – 47 = 6 5th Day - 40 Planned order = 5 Total Receipts on day = 0 Available = 6 (1 + 5) – 40 = - 34 Shortage 6th Day - 20 Receipt Day’s Supply on Today = Coverage’s Considering the receipts
  • 27. = 5 – 1 + (6/40) = 4 + 0.15 = 4.15 Days