第二讲(Introduction to production control system 2##37)、
1、summary
*Introduction to production control system.
- Supply chain planning
- Master data
- Demand planning
- Demand management
• Make-to-stock production
• Make-to-order production ✔
- Material requirement planning
- Long term planning
- Order-controlled production orders
- (Order-controlled production with process orders)
- (Repetitive manufacturing)
- (KANBAN)
2、sales order-related production
*Planning strategy of sales-order related production
- Make-to-order production(20)
- Planning with final assembly(50)
- Planning with material(60)
- Assembly processing(82)
3、make-to-order in production
*set up make to order
-change material master R-F1##,in MRP3 change the strategy to “20” which means make-to-order.
*create a sales order
4、set up make to order
*Logistics->Production->Master Data->Material Master->Material->Change->MM02-Immediately
5、create a sales order
*Logistics->Sales and Distribution->Sales->Order->VA01-Create
6、Planning and evaluating MRP for make-to-order
*Perform single item multi-level material requirements planning for R-F1##.
*then review the stock/requirements list.
7、perform MRP planning
*Logistics->Production ->MRP->Planning->MD02-Multilevel Single-Item Planning
8、review the stock/requirements list
*Logistics->Production->MRP->Evaluations->MD04-Stock/Requirements List
9、availability check
*Availability check
- Forecast the availability of a product.
*Options for availability check
- ATP(Available to promise)
#Check for each location.
- Forecast check
#Check consumption of planned independent requirement.
10、ATP(available to promise) in the sales order
*Logistics->Sales and Distribution->Sales->Order->VA01-Create
11、summary
*Introduction to production control system.
- Supply chain planning
- Master data
- Demand planning
- Demand management
• Make-to-stock production
• Make-to-order production
- Material requirement planning ✔
- Long term planning
- Order-controlled production orders
- (Order-controlled production with process orders)
- (Repetitive manufacturing)
- (KANBAN)
12、material requirement planning
13、record point planning
14、recorder point
15、record point planning
*ln reorder point planning, procurement is triggered when the sum of plant stock and firmed receipts falls below the reorder point.
*The reorder point should cover the average material requirements expected during the replenishment lead time.
16、procurement type
*Procurement type
- E(ln-house production)
- F(External procurement)
- X(both procurement types)
*Special procurement
- ln-house production
#80(Production in another plant)
- External procurement
#Stock transfer from another plant
#Subcontracting
17、planning material requirements
*Planning
- Total planning
#Online
#As a background job
- Single-item planning(for a specific material)
#Single-item planning multilevel
#Single-item planning single-level
#Single-item planning interactive
18、MRP control parameter
*processing key
-define a planning type
*purchase requisition and scheduling-agreement schedule lines
*MRP list
*planning mode
19、processing key
*Processing key
- NEUPL(regenerative planning)
#Plans all material in a plant.
- NETCH(Net change for total horizon)
#Planning of all materials to which an MRP-relevant change has been made.
- NETPL
#Planning of all materials to which an MRP-relevant change has
been made within the planning horizon.
#Planning within the planning horizon only.
20、planned order
*planned order
-backward scheduling for in-house production
-forward scheduling for in-house production
21、backward scheduling for in-house production
22、forward scheduling for in-house production
23、planned orders(in-house production)
24、planned orders(external procurement)
25、overview of the stock requirements
*Logistics->Production->MRP->Evaluations-> MD04-Stock/Requirements List
26、goods receipt
*Logistics->Material Management->Inventory Management->Goods Movement->MB1C-Other
27、execute MRP
*Logistics->Production->MRP->Planning->MD02-Multievel Single-Item Planning
28、summary
*Introduction to production control system.
- Supply chain planning
- Master data
- Demand planning
- Demand management
• Make-to-stock production
• Make-to-order production
- Material requirement planning
- Long term planning ✔
- Order-controlled production orders
- (Order-controlled production with process orders)
- (Repetitive manufacturing)
- (KANBAN)
29、long-term planning
*ln long-term planning, different versions of future demand programs are first calculated as simulations in the MRP.
*After the simulative planning results are evaluated, the previous demand program can be replaced and updated with the preferred version of long-term planning.
*Simulative planning areas
- ln long-term planning,independent planning area can be created.
- Each planning area has its own simulation data.
- That means each scenario has its own simulative planning area.
*Planning scenario
- Long-term planning
- Gross long-term planning
- Short-term simulation
- copy parameters from other scenario
30、create long-term planning scenario
*Logistics->Production->Production Planning->Long-term Planning->Scenario->MS31-Create
31、long-term planning situation
*Logistics->Production->Production Planning->Long-term Planning->Evaluation->MS04-Stock/Reqmts List
32、the long-term planning process
*After evaluating the simulative planning results,the required planned independent requirements version can be activated.
*After the planned independent requirements version has been activated, it becomes relevant for operative planning. You can also transfer simulative planned orders from long-term planning to operative planning.
33、the long-term planning run
*Logistics->Production->Production Planning->Long-term Planning->Long-term Planning->MS02-Multilevel Single-Item Planning
34、evaluate the planning results
*Logistics->Production->Production Planning->Long-term Planning->Evaluation->MS04-Stock/Reqmts List
35、evaluate capacity in long-term planning
36、release the long-term plan
*Logistics->Production->Production Planning->Long-term Planning->Scenatio->MS32-Change
37、access the operative current stock/requirements list